Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 20/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1630 MW
The minimum capacity reserve available is 1028 MW
Manager NEM Real Time Operations
CHG0089836 | Pre-Production | Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: Renewal and update of AEMO's FBS-Test-Hub.aemo.com.au server certificate.
Change Start Date & Time: 11/06/2024 10:00:00 AEST
Change End Date & Time: 11/06/2024 17:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Pre-Production
Participant Impact and Requirements: AEMO's FRC Gas Hub web services need to have their server certificates updated every year with new certificates to replace the xpiring one.
Participants connecting to these endpoints or receiving requests from AEMO's FRC Gas Hub platforms and have authorisation mechanisms like certificate fingerprinting in place will notice a change in AEMO's server's certificate fingerprint and will need to update their systems accordingly.
The certificate relates to "FBS-Test-Hub.aemo.com.au" certificate and relates to the following domains.
FBS-Test-Hub.aemo.com.au
apis.preprod.aemo.com.au
preprodhub.aemo.com.au
preprod.frchub.net
apis.preprod.marketnet.net.au
preprodhub.marketnet.net.au
Participants WILL need to update the profile that communicates with the above domains.
This will need to be done to avoid the inability to send messages to the relay.
The certificates can be downloaded from the link below:
https://www.digicert.com/secure/download-certificate/m7lnm6qjq6lgqn5kn228qt11d6x9qxv
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities.
CHG0089648 | Pre-Production | NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 16 May until 12pm (EST)
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Supply Hub
Change Title: NOR Pre-Prod GSH will have scheduled maintenance works outage from 9.00am Thursday 16 May until 12pm (EST)
Change Start Date & Time: 16/05/2024 09:00:00 AEST
Change End Date & Time: 16/05/2024 12:00:00 AEST
Outage Start Date & Time: 16/05/2024 09:00:00 AEST
Outage End Date & Time: 16/05/2024 12:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Services may be unavailable while maintenance is in progress
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024
Cancellation of Actual (LOR1) condition in the NSW region - 18/05/2024
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116688 is cancelled at 1840 hrs 18/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 18/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs
The capacity reserve requirement is 1430 MW
The minimum capacity reserve available is 1314 MW
Manager NEM Real Time Operations
CHG0089703 | Production | Planned System Maintenance activity.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMS NEM - Network Outage Scheduler (NOS)
Change Title: Planned System Maintenance activity.
Change Start Date & Time: 22/05/2024 11:00:00 AEST
Change End Date & Time: 22/05/2024 11:30:00 AEST
Outage Start Date & Time: 22/05/2024 11:00:00 AEST
Outage End Date & Time: 22/05/2024 11:30:00 AEST
Environment: Production
Participant Impact and Requirements: Network Outage Schedular (NOS) will be out of service during the maintenance activity. Please log off from NOS website during the outage. Users will have to log back in once the outage is completed. Please contact your NOS admin or AEMO support hub if your NOS account has been locked out after this change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
Cancellation of Actual (LOR1) condition in the Qld Region - 14/05/2024
Cancellation of Actual (LOR1) condition in the Qld region - 14/05/2024
The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.116615 is cancelled at 1815 hrs 14/05/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 14/05/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 14/05/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1800 hrs.
The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 727 MW.
Manager NEM Real Time Operations
CHG0089066 | Production | Dispatch Applications Upgrade
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: Dispatch Applications Upgrade
Change Start Date & Time: 22/05/2024 08:00:00 AEST
Change End Date & Time: 24/05/2024 17:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements:
Under this change , AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch ,5-Minute Predispatch ,Predispatch, PD7 and PASA as part of the Integrating Energy Storage Systems project (IESS). This change will become effective upon rule commencement on 3 June, 2024.
No outage required.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any