114607LOAD SHED13/02/2024 02:35:06 PM

Load Shedding Direction in the Vic Region

AEMO ELECTRICITY MARKET NOTICE

Load Shedding Direction in the Vic Region

AEMO has directed load shedding commencing at 1420 hrs 13/02/2024
in the Victoria region to restore power system security.

The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.

Manager NEM Real Time Operations
114604RESERVE NOTICE13/02/2024 02:27:41 PM

Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024

Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.

An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.

The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024

Manager NEM Real Time Operations
114563NON-CONFORMANCE13/02/2024 12:10:15 PM

NON-CONFORMANCE Region QLD1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 13/02/2024 12:05 to 13/02/2024 12:10
Amount: 15 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114556NON-CONFORMANCE13/02/2024 11:25:22 AM

NON-CONFORMANCE Region QLD1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 13/02/2024 11:10 to 13/02/2024 11:25
Amount: 10 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114543NON-CONFORMANCE13/02/2024 08:50:21 AM

NON-CONFORMANCE Region SA1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WATERLWF
Duration: 13/02/2024 08:15 to 13/02/2024 08:50
Amount: 43 MW
Constraint: NC-S_WATERLWF

Auto-generated on behalf of Manager NEM Real Time Operations
114542NON-CONFORMANCE13/02/2024 05:00:12 AM

NON-CONFORMANCE Region NSW1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MP1
Duration: 13/02/2024 04:55 to 13/02/2024 05:00
Amount: 21 MW
Constraint: NC-N_MP1

Auto-generated on behalf of Manager NEM Real Time Operations
114540NON-CONFORMANCE12/02/2024 08:25:15 PM

NON-CONFORMANCE Region QLD1 Monday, 12 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 12 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SWAN_E
Duration: 12/02/2024 20:15 to 12/02/2024 20:25
Amount: -63 MW
Constraint: NC-Q_SWAN_E

Auto-generated on behalf of Manager NEM Real Time Operations
114529NON-CONFORMANCE12/02/2024 01:40:10 PM

NON-CONFORMANCE Region VIC1 Monday, 12 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 12 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: BALBG1, BALBL1
Aggregate Dispatch Group: BALBESS_ADG1
Duration: 12/02/2024 13:30 to 12/02/2024 13:40
Amount: 23 MW
Constraint: NC-V_BALBESS_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
114523NON-CONFORMANCE12/02/2024 11:41:06 AM

NON-CONFORMANCE Region NSW1 Monday, 12 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 12 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: RIVNBG2, RIVNBL2
Aggregate Dispatch Group: RESS2_ADG1
Duration: 12/02/2024 11:35 to 12/02/2024 11:40
Amount: 50 MW
Constraint: NC-N_RESS2_ADG1