Market Notices

119882RESERVE NOTICE04/11/2024 06:18:07 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1135 MW
The minimum capacity reserve available is 875 MW

Manager NEM Real Time Operations
     
119845MARKET SYSTEMS04/11/2024 07:46:34 AM

CHG0099569 | Production | Maintenance on Gas B2B Hub databases

Change Number: CHG0099569
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal

Service/ Component: Gas Hub
Change Title: Maintenance on Gas B2B Hub databases
Change Start Date & Time: 17/11/2024 10:00:00 AEST
Change End Date & Time: 17/11/2024 10:30:00 AEST

Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: The following impacts are expected during this maintenance:
- Brief 5 to 10 seconds loss of connectivity to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) during the outage window.
- Users are not required to take any action due to this change.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.

Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .

     
119714RESERVE NOTICE31/10/2024 06:43:53 PM

Cancellation of Actual (LOR1) condition in the QLD region - 31/10/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 31/10/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.119713 is cancelled at 1839 hrs 31/10/2024.

Manager NEM Real Time Operations
     
119713RESERVE NOTICE31/10/2024 06:22:56 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 31/10/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 31/10/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The forecast capacity reserve requirement is 1298 MW.
The minimum capacity reserve available is 1178 MW.

Manager NEM Real Time Operations
     
119701NON-CONFORMANCE31/10/2024 02:01:14 PM

NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE Region NSW1 Thursday, 31 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:.

Unit: MP1
Duration: 31/10/2024 13:25 to 31/10/2024 13:30
Amount: -52 MW
Constraint: NC-N_MP1

Manager NEM Real Time Operations
     
119699NON-CONFORMANCE31/10/2024 01:05:15 PM

NON-CONFORMANCE Region QLD1 Thursday, 31 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Thursday, 31 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 31/10/2024 12:50 to 31/10/2024 13:05
Amount: 24 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
119567NON-CONFORMANCE28/10/2024 12:55:17 PM

NON-CONFORMANCE Region SA1 Monday, 28 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 28 October 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: TB2BG1, TB2BL1
Aggregate Dispatch Group: TB2HYB_ADG1
Duration: 28/10/2024 12:05 to 28/10/2024 12:55
Amount: 39 MW
Constraint: NC-S_TB2HYB_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
     
119500NON-CONFORMANCE27/10/2024 03:40:21 PM

NON-CONFORMANCE Region NSW1 Sunday, 27 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 27 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 27/10/2024 15:35 to 27/10/2024 15:40
Amount: -78 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
     
119499MARKET SYSTEMS27/10/2024 03:30:17 PM

CHG0098814 | Completed | Production | MSATS and eMDM November Maintenance Release

Change Number: CHG0098814
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS and eMDM November Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm