CHG0098193 | Production | AEMO will be undertaking maintenance activities on the RCM system
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Cohesity
Change Title: AEMO will be undertaking maintenance activities on the RCM system
Change Start Date & Time: 11/09/2024 20:00:00 AEST
Change End Date & Time: 12/09/2024 02:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: AEMO will be undertaking maintenance activities on the NEMSETTLEMENTSR system. Whilst no outage is expected there is potential for transient performance degradation during the change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
[EventId:202409081835_review] Prices for interval 08-Sep-2024 18:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1830 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409081830_review] Prices for interval 08-Sep-2024 18:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1825 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409081825_review] Prices for interval 08-Sep-2024 18:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1820 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409081820_review] Prices for interval 08-Sep-2024 18:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1815 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409081815_review] Prices for interval 08-Sep-2024 18:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 1810 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202409081810_review] Prices for interval 08-Sep-2024 18:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1805 hrs on 8 September 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 08-Sep-2024 18:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Update - Non-credible contingency event - VIC region - 06/09/2024
Update - Non-credible contingency event - VIC region - 06/09/2024
Refer AEMO Electricity Market Notice 118166
At 2005 hrs the Loy Yang PS No. 4 500 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 06/09/2024
Non-credible contingency event - VIC region - 06/09/2024
At 1222 hrs the Loy Yang PS No. 4 500 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations