Filter by category
Filter by Date
Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown
Duration: 31/05/2024 00:24 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202405230600_review] Prices for interval 23-May-2024 06:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0555 hrs on 23 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 23-May-2024 06:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405230555_review] Prices for interval 23-May-2024 05:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0550 hrs on 23 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 23-May-2024 05:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405230550_review] Prices for interval 23-May-2024 05:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0545 hrs on 23 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 23-May-2024 05:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405230545_review] Prices for interval 23-May-2024 05:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 0540 hrs on 23 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 23-May-2024 05:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405230540_review] Prices for interval 23-May-2024 05:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 0535 hrs on 23 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 23-May-2024 05:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405230535_review] Prices for interval 23-May-2024 05:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 0530 hrs on 23 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 23-May-2024 05:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405222100_review] Prices for interval 22-May-2024 21:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 2055 hrs on 22 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-May-2024 21:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405222055_review] Prices for interval 22-May-2024 20:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 2050 hrs on 22 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 22-May-2024 20:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.