114421NON-CONFORMANCE07/02/2024 03:50:18 PM

NON-CONFORMANCE Region QLD1 Wednesday, 7 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 7 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 07/02/2024 15:40 to 07/02/2024 15:50
Amount: -37 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114416NON-CONFORMANCE07/02/2024 02:05:15 PM

NON-CONFORMANCE Region VIC1 Wednesday, 7 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 7 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: GLRWNSF1
Duration: 07/02/2024 14:00 to 07/02/2024 14:05
Amount: 103 MW
Constraint: NC-V_GLRWNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
114415GENERAL NOTICE07/02/2024 01:50:29 PM

QNI Minor testing (NSW to Qld) 7th February 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 113265

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Wednesday 7th February 2024 from 1400 to 1800hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
114401RESERVE NOTICE06/02/2024 07:43:29 PM

Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.114399 is cancelled at 1945 hrs 06/02/2024.

Manager NEM Real Time Operations
114399RESERVE NOTICE06/02/2024 07:22:16 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

The actual LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 114397 has been updated at 1915 hrs 06/02/2024 to the following:

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1045 MW.
The minimum capacity reserve available is 950 MW.

Manager NEM Real Time Operations
114397RESERVE NOTICE06/02/2024 06:08:41 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1095 MW
The minimum capacity reserve available is 892 MW

Manager NEM Real Time Operations
114358GENERAL NOTICE06/02/2024 10:12:57 AM

Fast Frequency Response Market - Increase in L1 FCAS dispatch cap from 12 February 2024.

AEMO ELECTRICITY MARKET NOTICE

Following review of the operation of the Very Fast FCAS market, from 1300 hrs AEST on Monday 12 Febraury AEMO will:

Increase the cap on dispatch of Very Fast Lower (L1) Contingency FCAS from 100 MW to 125 MW

Retain the cap on dispatch of Very Fast Raise (R1) Contingency FCAS at 225 MW

No other changes to the dispatch of Very Fast FCAS or FCAS constraint equation changes will be made on this date.

For information on the Fast Frequency Response (FFR) initiative please visit the website at: https://www.aemo.com.au/initiatives/major-programs/fast-frequency-response

Andrew Groom
AEMO Operations
114293NON-CONFORMANCE05/02/2024 12:25:12 PM

NON-CONFORMANCE Region NSW1 Monday, 5 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 5 February 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: RIVNBG2, RIVNBL2
Aggregate Dispatch Group: RESS2_ADG1
Duration: 05/02/2024 12:15 to 05/02/2024 12:25
Amount: 49 MW
Constraint: NC-N_RESS2_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
114282NON-CONFORMANCE05/02/2024 09:40:12 AM

NON-CONFORMANCE Region NSW1 Monday, 5 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 4 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SEBSF1
Duration: 04/02/2024 12:45 to 05/02/2024 09:40
Amount: 35 MW
Constraint: NC-N_SEBSF1

Auto-generated on behalf of Manager NEM Real Time Operations