NON-CONFORMANCE Region VIC1 Monday, 7 October 2024
NON-CONFORMANCE VIC1 Region Monday, 7 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STOCKYD1
Duration: 07/10/2024 13:25 to 07/10/2024 15:10
Amount: 62 MW
Constraint: NC-V_STOCKYD1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Monday, 7 October 2024
NON-CONFORMANCE VIC1 Region Monday, 7 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: STOCKYD1
Duration: 07/10/2024 11:25 to 07/10/2024 13:10
Amount: 101 MW
Constraint: NC-V_STOCKYD1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 7 October 2024
NON-CONFORMANCE NSW1 Region Monday, 7 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WAGGNSF1
Duration: 07/10/2024 09:55 to 07/10/2024 10:15
Amount: 49 MW
Constraint: NC-N_WAGGNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region SA1 Sunday, 6 October 2024
NON-CONFORMANCE SA1 Region Sunday, 6 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: LKBONNY2
Duration: 06/10/2024 23:05 to 06/10/2024 23:10
Amount: 73 MW
Constraint: NC-S_LKBONNY2
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Sunday, 6 October 2024
NON-CONFORMANCE NSW1 Region Sunday, 6 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WTAHB1
Duration: 06/10/2024 13:00 to 06/10/2024 13:25
Amount: 9 MW
Constraint: NC-N_WTAHB1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Sunday, 6 October 2024
NON-CONFORMANCE QLD1 Region Saturday, 5 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 05/10/2024 20:05 to 06/10/2024 08:20
Amount: -56 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Saturday, 5 October 2024
NON-CONFORMANCE QLD1 Region Saturday, 5 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_1
Duration: 05/10/2024 18:45 to 05/10/2024 19:15
Amount: 37 MW
Constraint: NC-Q_MPP_1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition - NEM region.
AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 118600 is no longer reasonably possible and accordingly its classification has reverted to non-credible.
Cancellation time: 1130 hrs 05/10/2024.
No constraints were invoked during this event
Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Saturday, 5 October 2024
NON-CONFORMANCE NSW1 Region Saturday, 5 October 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: WYASF1
Duration: 05/10/2024 10:30 to 05/10/2024 11:05
Amount: 31 MW
Constraint: NC-N_WYASF1
Auto-generated on behalf of Manager NEM Real Time Operations