Market Notices

118663NON-CONFORMANCE07/10/2024 03:12:48 PM

NON-CONFORMANCE Region VIC1 Monday, 7 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 7 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STOCKYD1
Duration: 07/10/2024 13:25 to 07/10/2024 15:10
Amount: 62 MW
Constraint: NC-V_STOCKYD1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118643NON-CONFORMANCE07/10/2024 01:10:15 PM

NON-CONFORMANCE Region VIC1 Monday, 7 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 7 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: STOCKYD1
Duration: 07/10/2024 11:25 to 07/10/2024 13:10
Amount: 101 MW
Constraint: NC-V_STOCKYD1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118638NON-CONFORMANCE07/10/2024 10:15:28 AM

NON-CONFORMANCE Region NSW1 Monday, 7 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 7 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WAGGNSF1
Duration: 07/10/2024 09:55 to 07/10/2024 10:15
Amount: 49 MW
Constraint: NC-N_WAGGNSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118635NON-CONFORMANCE06/10/2024 11:32:58 PM

NON-CONFORMANCE Region SA1 Sunday, 6 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Sunday, 6 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: LKBONNY2
Duration: 06/10/2024 23:05 to 06/10/2024 23:10
Amount: 73 MW
Constraint: NC-S_LKBONNY2

Manager NEM Real Time Operations
     
118631NON-CONFORMANCE06/10/2024 01:25:28 PM

NON-CONFORMANCE Region NSW1 Sunday, 6 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 6 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 06/10/2024 13:00 to 06/10/2024 13:25
Amount: 9 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118627NON-CONFORMANCE06/10/2024 08:20:19 AM

NON-CONFORMANCE Region QLD1 Sunday, 6 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 5 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 05/10/2024 20:05 to 06/10/2024 08:20
Amount: -56 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
118624NON-CONFORMANCE05/10/2024 07:15:20 PM

NON-CONFORMANCE Region QLD1 Saturday, 5 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 5 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_1
Duration: 05/10/2024 18:45 to 05/10/2024 19:15
Amount: 37 MW
Constraint: NC-Q_MPP_1

Auto-generated on behalf of Manager NEM Real Time Operations
     
118609RECLASSIFY CONTINGENCY05/10/2024 11:40:36 AM

Cancellation: Reclassification of non-credible contingency event due to existence of widespread abnormal condition - NEM region.

AEMO ELECTRICITY MARKET NOTICE.

AEMO considers the occurrence of a non-credible contingency event due to the widespread abnormal conditions advised in AEMO Electricity Market Notice 118600 is no longer reasonably possible and accordingly its classification has reverted to non-credible.

Cancellation time: 1130 hrs 05/10/2024.

No constraints were invoked during this event

Manager NEM Real Time Operations
     
118608NON-CONFORMANCE05/10/2024 11:05:23 AM

NON-CONFORMANCE Region NSW1 Saturday, 5 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Saturday, 5 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WYASF1
Duration: 05/10/2024 10:30 to 05/10/2024 11:05
Amount: 31 MW
Constraint: NC-N_WYASF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm