Market Notices

114428RECLASSIFY CONTINGENCY07/02/2024 06:28:10 PM

Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Duration: 07/02/2024 18:28 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
114427RECLASSIFY CONTINGENCY07/02/2024 05:41:35 PM

Reclassification of a Non-Credible Contingency Event: Strathmore ? Clare South No.7208 132 kV line and Strathmore ? Clare South tee King Creek No.7128/1 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Strathmore ? Clare South No.7208 132 kV and Strathmore ? Clare South tee King Creek No.7128/1 132 kV

Duration: 07/02/2024 17:41 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
114426RECLASSIFY CONTINGENCY07/02/2024 05:41:35 PM

Reclassification of a Non-Credible Contingency Event: Strathmore ? Clare South No.7208 132 kV line and Strathmore ? Clare South tee King Creek No.7128/2 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Strathmore ? Clare South No.7208 132 kV and Strathmore ? Clare South tee King Creek No.7128/2 132 kV

Duration: 07/02/2024 17:41 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
114424RECLASSIFY CONTINGENCY07/02/2024 05:18:49 PM

Cancellation of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Cancellation time: 07/02/2024 1715 hrs

Constraint set(s) revoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 114423

Auto-generated on behalf of Manager NEM Real Time Operations
114423RECLASSIFY CONTINGENCY07/02/2024 04:07:35 PM

Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Duration: 07/02/2024 16:07 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
114419RECLASSIFY CONTINGENCY07/02/2024 02:35:31 PM

Cancellation of the Reclassification of a Non Credible Contingency event to a Credible Event - Kareeya Power Station - Qld Region

AEMO ELECTRICITY MARKET NOTICE

Cancellation of the reclassification of a Non-Credible contingency event as a Credible contingency event in the Qld region.

Based on the advice from the asset owner, AEMO considers the trip of the Kareeya Power Station Units 1,2,3 and 4 is no longer reasonably possible. Accordingly, its classification has reverted to a non-credible contingency event.

Region: QLD

Elements: Kareeya Power Station Units 1,2,3 and 4

Cancellation time: 1430 hrs 07/02/2024

Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 113228

Manager NEM Real Time Operations
114413RECLASSIFY CONTINGENCY07/02/2024 12:18:10 PM

Cancellation - Reclassification of a Non-Credible Contingency Event: Darling Downs Power Station in Queensland Region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Reclassification of a Non-Credible Contingency Event: Darling Downs Power Station in Queensland Region - 06/02/2024

Refer to MN 114356

Based on advice from the asset owner, AEMO no longer considers the simultaneous trip of all the generators at Darling Downs Power Station as a credible contingency event.

Therefore AEMO cancels the reclassification as a credible contingency event from 1215 hrs 07/02/2024.

Constraint set Q-DARLING_DOWNS_N-2 revoked from 1215 hrs 07/02/2024

Manager NEM Real Time Operations
114411RECLASSIFY CONTINGENCY07/02/2024 04:35:47 AM

Cancellation of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Cancellation time: 07/02/2024 0435 hrs

Constraint set(s) revoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 114410

Auto-generated on behalf of Manager NEM Real Time Operations
114410RECLASSIFY CONTINGENCY06/02/2024 10:38:08 PM

Reclassification of a Non-Credible Contingency Event: Ross - Chalumbin No.857 275 kV line and Ross - Chalumbin No.858 275 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Ross - Chalumbin No.857 275 kV and Ross - Chalumbin No.858 275 kV

Duration: 06/02/2024 22:38 until further notice

Constraint set(s) invoked:
Q-RSCH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations