114401RESERVE NOTICE06/02/2024 07:43:29 PM

Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.114399 is cancelled at 1945 hrs 06/02/2024.

Manager NEM Real Time Operations
114399RESERVE NOTICE06/02/2024 07:22:16 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

The actual LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 114397 has been updated at 1915 hrs 06/02/2024 to the following:

The Actual LOR1 condition is forecast to exist until 2000 hrs.

The forecast capacity reserve requirement is 1045 MW.
The minimum capacity reserve available is 950 MW.

Manager NEM Real Time Operations
114397RESERVE NOTICE06/02/2024 06:08:41 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs

The capacity reserve requirement is 1095 MW
The minimum capacity reserve available is 892 MW

Manager NEM Real Time Operations
113998RESERVE NOTICE29/01/2024 08:23:46 PM

Cancellation of Actual (LOR1) condition in the QLD region - 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 29/01/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113994 is cancelled at 2000 hrs 29/01/2024.

Manager NEM Real Time Operations
113994RESERVE NOTICE29/01/2024 06:12:37 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 29/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1810 hrs.

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1197 MW.
The minimum capacity reserve available is 1026 MW.

Manager NEM Real Time Operations
113958RESERVE NOTICE29/01/2024 09:17:19 AM

STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the QLD Region on 01/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO considers that there are suspect Forecast LOR3 conditions for the QLD region for the following periods:

1. From 0900 hrs to 1000 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 38 MW at 0930 hrs.

2. From 1130 hrs to 1200 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 62 MW at 1130 hrs.

AEMO is currently investigating these LOR3 forecast conditions to confirm whether they are valid.

AEMO Operations
113892RESERVE NOTICE27/01/2024 08:46:54 PM

Cancellation of Actual (LOR1) condition in the QLD region - 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 27/01/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113871 is cancelled at 2045 hrs 27/01/2024.

Manager NEM Real Time Operations
113871RESERVE NOTICE27/01/2024 06:27:46 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 27/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1000 MW.
The minimum capacity reserve available is 664 MW.

Manager NEM Real Time Operations
113654INTER-REGIONAL TRANSFER23/01/2024 03:30:39 AM

Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Hazelwood - South Morang No2 500 kV Line - VIC region - 23/01/2024

At 0318 hrs 23/01/2024 there was an unplanned outage of Hazelwood - South Morang No2 500 kV Line.

The following constraint set(s) invoked at 0325 hrs 23/01/2024
V-HWSM

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1,V-S-MNSP1,V-SA,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations