114943MARKET SYSTEMS22/02/2024 10:51:39 AM

CHG0085807 | Pre-Production | MSATS - eMDM Pre-Production Maintenance AKS v1.27 upgrade

Change Number: CHG0085807
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: MSATS - eMDM Pre-Production Maintenance AKS v1.27 upgrade
Change Start Date & Time: 26/02/2024 12:00:00 AEST
Change End Date & Time: 26/02/2024 19:00:00 AEST
Outage Start Date & Time: 26/02/2024 12:00:00 AEST
Outage End Date & Time: 26/02/2024 16:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
114937MARKET SYSTEMS22/02/2024 09:56:46 AM

CHG0085737 | Pre-Production | Pre-production EMMS database refresh

Change Number: CHG0085737
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Electricity Market Management System
Change Title: Pre-production EMMS database refresh
Change Start Date & Time: 26/02/2024 08:00:00 AEST
Change End Date & Time: 17/03/2024 17:30:00 AEST
Outage Start Date & Time: 04/03/2024 08:00:00 AEST
Outage End Date & Time: 08/03/2024 19:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: The pre-production EMMS environment will be refreshed with production data (NEM, WARE, SETTLEMENTS & GSH databases).
The Electricity Market Management System (EMMS) and Gas Supply Hub (GSH) Pre-Production environment will be unavailable during the outage window.

Upon completion of the outage users will be required to log in to the GSH Trayport application using their Production credentials.Trayport passwords in Pre-Production environment will be replaced with their Production passwords
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
114925RECLASSIFY CONTINGENCY21/02/2024 04:54:25 PM

Cancellation of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV

Cancellation time: 21/02/2024 16:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 114919

Auto-generated on behalf of Manager NEM Real Time Operations
114924RECLASSIFY CONTINGENCY21/02/2024 04:54:25 PM

Cancellation of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV

Cancellation time: 21/02/2024 16:54

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 114920

Auto-generated on behalf of Manager NEM Real Time Operations
114923MARKET INTERVENTION21/02/2024 04:36:24 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0030 hrs 23/02/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
114921MARKET INTERVENTION21/02/2024 04:30:12 PM

Direction - SA region 21/02/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 21/02/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1635 hrs on 21/02/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
114920RECLASSIFY CONTINGENCY21/02/2024 03:49:05 PM

Reclassification of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV

Duration: 21/02/2024 15:49 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
114919RECLASSIFY CONTINGENCY21/02/2024 03:49:05 PM

Reclassification of a Non-Credible Contingency Event: Strathmore - Clare South No.7208 132 kV line and Strathmore - Clare South tee King Creek No.7128 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Strathmore - Clare South No.7208 132 kV and Strathmore - Clare South tee King Creek No.7128 132 kV

Duration: 21/02/2024 15:49 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
114918MARKET INTERVENTION21/02/2024 02:51:14 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 114916

The synchronous generating units currently expected to be synchronised in SA from 0700 hrs 22/02/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1630 hrs 21/02/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations