114647RECLASSIFY CONTINGENCY13/02/2024 04:33:56 PM

Reclassification of a Non-Credible Contingency Event: Norwood -Scottsdale 110kV line and the Norwood - Scottsdale -Derby 110kV line in TAS due to Non-Credible Event

AEMO ELECTRICITY MARKET NOTICE.

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Non-Credible Event. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS

Lines: Norwood -Scottsdale 110kV line and the Norwood - Scottsdale -Derby 110kV line

Duration: 13/02/2024 16:30 until further notice

Manager NEM Real Time Operations
114644RESERVE NOTICE13/02/2024 04:15:16 PM

Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the VIC region - 13/02/2024

The Actual LOR2 Condition in the VIC Region advised in AEMO Electricity Market Notice No.114589 is cancelled at 1614 hrs 13/02/2024.

Manager NEM Real Time Operations
114641RECLASSIFY CONTINGENCY13/02/2024 03:27:46 PM

Reclassification of non-credible contingency event due to existence of widespread abnormal conditions - VIC region(s).

AEMO ELECTRICITY MARKET NOTICE.

AEMO has identified that a non-credible contingency event impacting the power system is more likely to occur and is considered reasonably possible because of the existence of widespread abnormal conditions namely severe weather in the VIC region.

AEMO has therefore reclassified the occurrence of a non-credible contingency event involving multiple plant due to these abnormal conditions as credible.

Need for further measures is being monitored and further measures may be implemented in line with the Power System Security Guidelines (SO_OP_3715).

Manager NEM Real Time Operations
114640RECLASSIFY CONTINGENCY13/02/2024 03:21:30 PM

Reclassification of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Duration: 13/02/2024 15:21 until further notice

Constraint set(s) invoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
114630RECLASSIFY CONTINGENCY13/02/2024 03:12:35 PM

Reclassification of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE

Duration: 13/02/2024 15:12 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
114617NON-CONFORMANCE13/02/2024 02:55:18 PM

NON-CONFORMANCE Region VIC1 Tuesday, 13 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Tuesday, 13 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 13/02/2024 14:50 to 13/02/2024 14:55
Amount: -25 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
114611RECLASSIFY CONTINGENCY13/02/2024 02:40:01 PM

Cancellation of a Non-Credible Contingency Event: Palmerston - Hadspen 3 & 4 110kV line and line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Palmerston - Hadspen 3 & 4 110kV and

Cancellation time: 13/02/2024 14:39

Constraint set(s) revoked:
T-HAPM_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 114559

Auto-generated on behalf of Manager NEM Real Time Operations
114603MARKET INTERVENTION13/02/2024 02:18:14 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - VIC1 Region- 13/02/2024

Refer to AEMO Electricity Market Notice no. 114589.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
15:00 to 17:00 hrs 13/02/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations
114602MARKET INTERVENTION13/02/2024 02:18:13 PM

INTENTION TO COMMENCE RERT CONTRACT NEGOTIATIONS

AEMO ELECTRICITY MARKET NOTICE.
Reliability and Emergency Reserve Trader (RERT) Intention to negotiate for additional reserve - VIC1 Region- 13/02/2024

Refer to AEMO Electricity Market Notice no. 114589.
AEMO intends to commence negotiations with RERT Panel members for the provision of additional reserve by issuing requests for tender for the following period of time;
15:00 to 17:00 hrs 13/02/2024
If reserve is required, the period of activation or dispatch will be within this period but may not be for the entire period.
AEMO will issue a further advice if reserve is contracted.


Manager NEM Real Time Operations