Market Notices

113834RECLASSIFY CONTINGENCY27/01/2024 11:00:48 AM

Reclassification of a Non-Credible Contingency Event: Strathmore ? Clare South No.7208 132 kV line and Strathmore ? Clare South tee King Creek No.7128/1 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Strathmore ? Clare South No.7208 132 kV and Strathmore ? Clare South tee King Creek No.7128/1 132 kV

Duration: 27/01/2024 11:00 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
113833RECLASSIFY CONTINGENCY27/01/2024 10:32:35 AM

Reclassification of a Non-Credible Contingency Event: Strathmore ? Clare South No.7208 132 kV line and Strathmore ? Clare South tee King Creek No.7128/2 132 kV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Strathmore ? Clare South No.7208 132 kV and Strathmore ? Clare South tee King Creek No.7128/2 132 kV

Duration: 27/01/2024 10:32 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
113826NON-CONFORMANCE27/01/2024 03:25:10 AM

NON-CONFORMANCE Region SA1 Saturday, 27 January 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Saturday, 27 January 2024

AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:

Units: HPRG1, HPRL1
Aggregate Dispatch Group: HORNSDPR_ADG1
Duration: 27/01/2024 03:20 to 27/01/2024 03:25
Amount: 15 MW
Constraint: NC-S_HORNSDPR_ADG1

Auto-generated on behalf of Manager NEM Real Time Operations
113811PRICES SUBJECT TO REVIEW26/01/2024 07:00:13 PM

[EventId:202401261905_review] Prices for interval 26-Jan-2024 19:05 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1900 hrs on 26 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Jan-2024 19:05.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113810PRICES SUBJECT TO REVIEW26/01/2024 06:55:13 PM

[EventId:202401261900_review] Prices for interval 26-Jan-2024 19:00 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1855 hrs on 26 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Jan-2024 19:00.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113809PRICES SUBJECT TO REVIEW26/01/2024 06:50:17 PM

[EventId:202401261855_review] Prices for interval 26-Jan-2024 18:55 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1850 hrs on 26 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Jan-2024 18:55.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113808PRICES SUBJECT TO REVIEW26/01/2024 06:45:12 PM

[EventId:202401261850_review] Prices for interval 26-Jan-2024 18:50 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1845 hrs on 26 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Jan-2024 18:50.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113807PRICES SUBJECT TO REVIEW26/01/2024 06:40:17 PM

[EventId:202401261845_review] Prices for interval 26-Jan-2024 18:45 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1840 hrs on 26 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Jan-2024 18:45.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
113806PRICES SUBJECT TO REVIEW26/01/2024 06:35:18 PM

[EventId:202401261840_review] Prices for interval 26-Jan-2024 18:40 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1835 hrs on 26 January 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 26-Jan-2024 18:40.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.