Market Notices

118857MARKET INTERVENTION13/10/2024 02:41:31 PM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 118856

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 14/10/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 13/10/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
118856MARKET INTERVENTION13/10/2024 02:27:43 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0900 hrs 14/10/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
118855MARKET INTERVENTION13/10/2024 03:31:37 PM

Cancellation - AEMO Intervention Event - SA region 10/10/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 10/10/2024

Refer to Market Notice 118763

The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs on 13/10/2024.


Manager NEM Real Time Operations
     
118854MARKET INTERVENTION13/10/2024 03:29:58 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 118811

Direction is cancelled from: 1530 hrs 13/10/2024

Manager NEM Real Time Operations
     
118853MARKET INTERVENTION13/10/2024 02:58:06 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 118850

Direction is cancelled from: 1500 hrs 13/10/2024

Manager NEM Real Time Operations
     
118850MARKET INTERVENTION13/10/2024 12:01:09 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118830

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1500 hrs 13/10/2024.

The direction update is issued at 1200 hrs 13/10/2024.

Manager NEM Real Time Operations
     
118834MARKET INTERVENTION13/10/2024 07:17:57 AM

Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024

AEMO ELECTRICITY MARKET NOTICE
Minimum System Load 1 (MSL1) in the VIC Region on 13/10/2024

AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the Victorian region from 1100 hrs 13/10/2024 to 1300 hrs 13/10/2024.

Minimum regional demand is forecast to be 1493 MW at 1230 hrs, and the advisory threshold is:
- MSL1 - 1560 MW
- MSL2 - 1060 MW
- MSL3 - 560 MW

MSL events are forecast when forecast regional demand is less than the relevant MSL threshold. The forecast regional demand is below the MSL1 threshold. Refer to NEM Data Dashboard to monitor demand levels: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem
AEMO is seeking a market response such as rescheduling of planned network outages and increasing electricity consumption.
An insufficient market response may require AEMO to take action or intervene to maintain power system security in Victoria. This may result in actions such as recalling network outages, the direction of scheduled production units, curtailment of non-scheduled production units, and/or a direction to maintain regional demand above required MSL threshold, in both Victoria and South Australia.

Manager NEM Real Time Operations
     
118830MARKET INTERVENTION12/10/2024 09:29:16 PM

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118810

The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 13/10/2024.

The direction update is issued at 2130 hrs 12/10/2024.

Manager NEM Real Time Operations
     
118811MARKET INTERVENTION12/10/2024 01:57:09 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118772

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 13/10/2024.

The direction update is issued at 1400 hrs 12/10/2024.

Manager NEM Real Time Operations
     
X