113900RESERVE NOTICE28/01/2024 06:27:57 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113895 is cancelled at 0600 hrs 28/01/2024.

Manager NEM Real Time Operations
113898RESERVE NOTICE28/01/2024 05:39:14 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 30/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice 113896 has been updated at 0530 hrs 28/01/2024 to the following:

[1.] From 0830 hrs 30/01/2024 to 1030 hrs 30/01/2024.
The forecast capacity reserve requirement is 685 MW.
The minimum capacity reserve available is 584 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113896RESERVE NOTICE28/01/2024 12:44:58 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 30/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice 113872 has been updated at 0030 hrs 28/01/2024 to the following:

[1.] From 1430 hrs 30/01/2024 to 1530 hrs 30/01/2024.
The forecast capacity reserve requirement is 777 MW.
The minimum capacity reserve available is 771 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113895RESERVE NOTICE28/01/2024 12:46:13 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice 113889 has been updated at 0030 hrs 28/01/2024 to the following:

[[1.] From 1730 hrs 29/01/2024 to 1830 hrs 29/01/2024.
The forecast capacity reserve requirement is 1190 MW.
The minimum capacity reserve available is 1113 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113889RESERVE NOTICE27/01/2024 07:42:23 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1730 hrs 29/01/2024 to 1830 hrs 29/01/2024.
The forecast capacity reserve requirement is 1470 MW.
The minimum capacity reserve available is 1382 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113872RESERVE NOTICE27/01/2024 05:39:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 30/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113842 has been updated at 1700 hrs 27/01/24 to the following:

From 0800 hrs 30/01/2024 to 1600 hrs 30/01/2024.
The forecast capacity reserve requirement is 845 MW.
The minimum capacity reserve available is 516 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
113865RESERVE NOTICE27/01/2024 03:50:28 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113853 is cancelled at 1530 hrs 27/01/2024.

Manager NEM Real Time Operations
113853RESERVE NOTICE27/01/2024 02:19:30 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113840 has been updated at 1400 hrs to the following:

[From 1900 hrs 27/01/2024 to 1930 hrs 27/01/2024.
The forecast capacity reserve requirement is 520 MW.
The minimum capacity reserve available is 514 MW.

AEMO is seeking a market response.

Manager NEM Real Time Operations
113842RESERVE NOTICE27/01/2024 03:42:28 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 30/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113829 has been updated at 1400 hrs 27/01/24 to the following:

From 0800 hrs 30/01/2024 to 1300 hrs 30/01/2024.
The forecast capacity reserve requirement is 883 MW.
The minimum capacity reserve available is 505 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

AEMO Operations