[EventId:202404201300_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 20 April 2024 13:00
Issued by Australian Energy Market Operator Ltd at 1300 hrs on 20 April 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 April 2024.
Refer to market notice: 116210
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1300 hrs on 20 April 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202404201205_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 20 April 2024 12:05
Issued by Australian Energy Market Operator Ltd at 1205 hrs on 20 April 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 April 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1205 hrs on 20 April 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Update - Non-credible contingency event - VIC region - 17/04/2024
Update - Non-credible contingency event - VIC region - 17/04/2024
Refer AEMO Electricity Market Notice 116160
At 0610 hrs the Heywood No 2 500 kV bus was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - VIC region - 17/04/2024
Non-credible contingency event - VIC region - 17/04/2024
At 0414 hrs the Heywood No 2 500 kV bus tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - TAS region - 12/04/2024
Update - Non-credible contingency event - TAS region - 12/04/2024
Refer AEMO Electricity Market Notice 116095
At 1304 hrs the Sheffield - Farrell No.2 220 kV line was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - TAS region - 12/04/2024
Non-credible contingency event - TAS region - 12/04/2024
At 1048 hrs the Sheffield - Farrell No.2 220 kV line tripped during restoration due to fault on the line.
AEMO did not instruct load shedding.
AEMO has been advised of disconnection of major industrial load approximately 550 MW.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - QLD region - 10/04/2024
Update - Non-credible contingency event - QLD region - 10/04/2024
Refer AEMO Electricity Market Notice 116072
At 1540 hrs the Ingham South to Cardwell 132 kV line was returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.
Manager NEM Real Time Operations
Non-credible contingency event - QLD region - 10/04/2024
Non-credible contingency event - QLD region - 10/04/2024
At 0730 hrs the Ingham South to Cardwell 132 kV line tripped at the Ingham South end only.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
Update - Non-credible contingency event - SA region - 25/03/2024
Update - Non-credible contingency event - SA region - 25/03/2024
Refer AEMO Electricity Market Notice 115794
At 1736 hrs Torrens Island BC3 275 kV CB was returned to service.
Torrens Island BW3 275 kV CB and Torrens Island - Lefevre 275 kV line previously returned to service.
The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.
AEMO will not reclassify this event as a credible contingency event.