120124RECLASSIFY CONTINGENCY07/11/2024 09:59:25 PM

Cancellation of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Cancellation time: 07/11/2024 21:59

Constraint set(s) revoked:
NONE

Refer AEMO Electricity Market Notice 120119

Auto-generated on behalf of Manager NEM Real Time Operations
     
120122RESERVE NOTICE07/11/2024 09:29:31 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120080 has been updated at 2115 hrs to the following:

[[1.] From 1730 hrs 08/11/2024 to 1930 hrs 08/11/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1165 MW.

Manager NEM Real Time Operations
     
120121RESERVE NOTICE07/11/2024 09:24:15 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120083 has been updated at 2115 hrs to the following:

[1.] From 1730 hrs 08/11/2024 to 1800 hrs 08/11/2024.
The forecast capacity reserve requirement is 1085 MW.
The minimum capacity reserve available is 813 MW.

[2.] From 1900 hrs 08/11/2024 to 1930 hrs 08/11/2024.
The forecast capacity reserve requirement is 1066 MW.
The minimum capacity reserve available is 895 MW.

Manager NEM Real Time Operations
     
120120RESERVE NOTICE07/11/2024 09:23:02 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1800 hrs 08/11/2024 to 1900 hrs 08/11/2024.
The forecast capacity reserve requirement is 727 MW.
The minimum capacity reserve available is 694 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120119RECLASSIFY CONTINGENCY07/11/2024 08:55:10 PM

Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV

Duration: 07/11/2024 20:55 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
     
120118RECLASSIFY CONTINGENCY07/11/2024 08:49:26 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 07/11/2024 20:49

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 120116

Auto-generated on behalf of Manager NEM Real Time Operations
     
120116RECLASSIFY CONTINGENCY07/11/2024 07:45:51 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 07/11/2024 19:45 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     
120114RECLASSIFY CONTINGENCY07/11/2024 07:29:26 PM

Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Cancellation time: 07/11/2024 19:29

Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Refer AEMO Electricity Market Notice 120110

Auto-generated on behalf of Manager NEM Real Time Operations
     
120110RECLASSIFY CONTINGENCY07/11/2024 04:24:16 PM

Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: NSW1

Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV

Duration: 07/11/2024 16:24 until further notice

Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
     