118328MARKET INTERVENTION20/09/2024 08:44:04 AM

Update - Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Foreseeable AEMO intervention in SA region

Refer AEMO Electricity Market Notice 118327

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1930 hrs 20/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1200 hrs 20/09/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
118327MARKET INTERVENTION20/09/2024 07:27:04 AM

Foreseeable AEMO intervention in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention in SA region


AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1630 hrs 20/09/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

AEMO estimates that, in the absence of sufficient market response by 1430 hrs 20/09/2024, AEMO may need to intervene by issuing a direction.

Manager NEM Real Time Operations
     
118325MARKET INTERVENTION19/09/2024 04:57:32 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118315

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0900 hrs 20/09/2024.

The direction update is issued at 1700 hrs 19/09/2024.

Manager NEM Real Time Operations
     
118324MARKET INTERVENTION19/09/2024 04:56:14 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118316

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1530 hrs 20/09/2024.

The direction update is issued at 1700 hrs 19/09/2024.

Manager NEM Real Time Operations
     
118316MARKET INTERVENTION18/09/2024 04:56:06 PM

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118306

The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 20/09/2024.

The direction update is issued at 1700 hrs 18/09/2024.

Manager NEM Real Time Operations
     
118315MARKET INTERVENTION18/09/2024 04:54:45 PM

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE.

Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer AEMO Electricity Market Notice 118308

The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 20/09/2024.

The direction update is issued at 1700 hrs 18/09/2024.

Manager NEM Real Time Operations
     
118313MARKET SYSTEMS18/09/2024 12:09:04 PM

CHG0098133 | Production | NEM Reform - RMI (Retail Market Improvements) MSATS 54.0

Change Number: CHG0098133
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Market Settlement & Transfer System
Change Title: NEM Reform - RMI (Retail Market Improvements) MSATS 54.0
Change Start Date & Time: 29/09/2024 10:00:00 AEST
Change End Date & Time: 29/09/2024 17:00:00 AEST
Outage Start Date & Time: 29/09/2024 10:00:00 AEST
Outage End Date & Time: 29/09/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
118309MARKET INTERVENTION17/09/2024 03:26:08 PM

Direction - SA region 17/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 17/09/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1535 hrs on 17/09/2024.

Intervention pricing does not apply to this AEMO intervention event.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.


Manager NEM Real Time Operations
     
118308MARKET INTERVENTION17/09/2024 03:27:27 PM

Direction - SA region 17/09/2024

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region 17/09/2024

Refer to Market Notice 118302


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1530 hrs 17/09/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 2200 hrs 17/09/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 19/09/2024

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.