112745INTER-REGIONAL TRANSFER25/12/2023 09:37:47 PM

Inter-regional transfer limit variation - Greenbank - Molendinar 8824 275 kV line - QLD region - 25/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank - Molendinar 8824 275 kV line - QLD region - 25/12/2023

At 2057 hrs 25/12/2023 there was an unplanned outage of Greenbank - Molendinar 8824 275 kV line

The outage has been returned to service at 2125 hrs 25/12/2023

Constraint set(s) invoked: Q-GBMO_8824_8825 from 2105 hrs to 2125 hrs


This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112621INTER-REGIONAL TRANSFER23/12/2023 12:38:04 PM

Inter-regional transfer limit variation - Palmerston - Hadspen 220 kV Line - TAS region - 23/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Palmerston - Hadspen 220 kV Line - TAS region - 23/12/2023

A planned outage of Palmerston - Hadspen 220 kV Line in the TAS region was scheduled from 1000 hrs 23/12/2023 to 1500 hrs 23/12/2023.

The outage has been completed and returned to service at 1045 hrs 23/12/2023

Constraint set(s) invoked:
T-HAPM_220

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V- MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112613INTER-REGIONAL TRANSFER23/12/2023 06:39:17 AM

Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - [outage element] - NSW region - 23/12/2023


A planned outage of KEMPS CREEK No 2 525/345/34 kV Transformer in the NSW region was scheduled from 0600 hrs 23/12/2023 to 1200 hrs 23/12/2023.

The outage has been cancelled.

The following constraint set(s) invoked at 0600 hrs 23/12/2023
N-KC_TX

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q_MNSP1
NSW1-QLD1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112590INTER-REGIONAL TRANSFER22/12/2023 01:01:28 PM

Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Palmerston - Hadspen 2 220kV line - TAS region - 22/12/2023

At 1300 hrs 22/12/2023 there was a short notice outage of Palmerston - Hadspen 2 220kV line.

Constraint set(s) invoked: T-HAPM_220


This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V - MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112559GENERAL NOTICE21/12/2023 09:53:10 AM

QNI Minor testing (NSW to Qld) 21st December 2023

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 112396

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Thursday 21st December from 1400 to 1700hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
112433INTER-REGIONAL TRANSFER17/12/2023 06:09:07 AM

Inter-regional transfer limit variation: Hazelwood - South Morang No 1 500 kV Line (VIC) - Voltage Control

AEMO ELECTRICITY MARKET NOTICE

The Hazelwood - South Morang No 1 500 kV Line has been de-energised to manage voltages in the Victoria region.

The following constraint set was invoked at 0600 hrs 17/12/2023

V-HWSM

The constraint set contains equations with the following interconnectors on the LHS.

T-V-MNSP
V-S-MNSP1
V-SA
VIC1-NSW1

Refer to AEMO Network Outage Scheduler (NOS) for return to service details

Manager NEM Real Time Operations
112432INTER-REGIONAL TRANSFER17/12/2023 05:48:19 AM

Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Sydney West - Vineyard No 29 330kV line - NSW region - 17/12/2023

At 0545 hrs 17/12/2023 there was a short notice outage of Sydney West - Vineyard No 29 330kV line.

Constraint set(s) invoked: N-SWVY_29

The following constraint set(s) invoked at 0545 hrs 17/12/2023
N-SWVY_29

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
112396GENERAL NOTICE16/12/2023 09:14:41 AM

QNI Minor testing (NSW to Qld) 16th December 2023

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 110640

There is an opportunity for testing QNI Minor for flows from NSW to Qld up to 750 MW on Tuesday 16th December from 0930 to 1800hrs.

This test includes a trip and reclose of a line in northern NSW.

Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade

Ben Blake
AEMO Operations
112373GENERAL NOTICE15/12/2023 10:10:57 AM

Network Augmentation Commissioned - SA Region - 15/12/2023

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - SA Region - 15/12/2023

Commissioned:
Bundey 330kV substation, 330kV East Bus and 330kV West Bus.