Filter by category
Filter by Date
CHG0087670 | Completed | Production | MSATS-CATS Production Maintenance
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS-CATS Production Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0088386 | Cancelled | Production | QLD Internet Router Refresh
Notification issued to: Market Notice
Notification Type: Cancelled
Change Type: Normal
Service/ Component: Internet Access
Change Title: QLD Internet Router Refresh
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600
NON-CONFORMANCE Region VIC1 Friday, 3 May 2024
NON-CONFORMANCE VIC1 Region Friday, 3 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: YWPS3
Duration: 03/05/2024 07:00 to 03/05/2024 07:10
Amount: -45 MW
Constraint: NC-V_YWPS3
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Friday, 3 May 2024
NON-CONFORMANCE NSW1 Region Friday, 3 May 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: BW04
Duration: 03/05/2024 06:20 to 03/05/2024 06:35
Amount: -43 MW
Constraint: NC-N_BW04
Auto-generated on behalf of Manager NEM Real Time Operations
Network Augmentation Commissioned - QLD Region - 02/05/2024
Network Augmentation Commissioned - QLD Region - 02/05/2024
Commissioned:
H13 Ross - H93 Guybal Munjan No.8917 275 kV line
Manager NEM Real Time Operations
CHG0089106 | Completed | Pre-Production | Pre-Prod eMDM May Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Pre-Prod eMDM May Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0088824 | Production | NEM Reform IESS Retail MSATS 53.0 Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: NEM Reform IESS Retail MSATS 53.0 Release
Change Start Date & Time: 12/05/2024 09:00:00 AEST
Change End Date & Time: 12/05/2024 17:00:00 AEST
Outage Start Date & Time: 12/05/2024 10:00:00 AEST
Outage End Date & Time: 12/05/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0089106 | Pre-Production | Pre-Prod eMDM May Maintenance Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: Pre-Prod eMDM May Maintenance Release
Change Start Date & Time: 02/05/2024 13:00:00 AEST
Change End Date & Time: 02/05/2024 21:00:00 AEST
Outage Start Date & Time: 02/05/2024 13:00:00 AEST
Outage End Date & Time: 02/05/2024 17:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region NSW1 Monday, 29 April 2024
NON-CONFORMANCE NSW1 Region Monday, 29 April 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: VP5
Duration: 29/04/2024 20:50 to 29/04/2024 20:55
Amount: -18 MW
Constraint: NC-N_VP5
Auto-generated on behalf of Manager NEM Real Time Operations