NON-CONFORMANCE Region VIC1 Monday, 12 February 2024
NON-CONFORMANCE VIC1 Region Monday, 12 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: BALBG1, BALBL1
Aggregate Dispatch Group: BALBESS_ADG1
Duration: 12/02/2024 13:30 to 12/02/2024 13:40
Amount: 23 MW
Constraint: NC-V_BALBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 12 February 2024
NON-CONFORMANCE NSW1 Region Monday, 12 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: RIVNBG2, RIVNBL2
Aggregate Dispatch Group: RESS2_ADG1
Duration: 12/02/2024 11:35 to 12/02/2024 11:40
Amount: 50 MW
Constraint: NC-N_RESS2_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region NSW1 Monday, 12 February 2024
NON-CONFORMANCE NSW1 Region Monday, 12 February 2024
AEMO has declared the following units comprising an Aggregate Dispatch Group as non-conforming under clause 3.8.23 of the National Electricity Rules:
Units: DPNTBG1, DPNTBL1
Aggregate Dispatch Group: DPNTBESS_ADG1
Duration: 12/02/2024 11:35 to 12/02/2024 11:40
Amount: 25 MW
Constraint: NC-N_DPNTBESS_ADG1
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 10 February 2024
NON-CONFORMANCE VIC1 Region Saturday, 10 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GANNSF1
Duration: 10/02/2024 10:40 to 10/02/2024 10:55
Amount: 25 MW
Constraint: NC-V_GANNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
CHG0083624 | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Change Start Date & Time: 18/02/2024 09:00:00 AEST
Change End Date & Time: 18/02/2024 17:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production
Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the Electricity B2B Hub will be unavailable.
- All access to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) will be unavailable. CATS and MDMT transactions for VIC/QLD will be delayed during the maintenance window.
- Users are not required to take any action due to this change, however will need to enact manual workarounds for the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
NON-CONFORMANCE Region QLD1 Wednesday, 7 February 2024
NON-CONFORMANCE QLD1 Region Wednesday, 7 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: MPP_2
Duration: 07/02/2024 15:40 to 07/02/2024 15:50
Amount: -37 MW
Constraint: NC-Q_MPP_2
Auto-generated on behalf of Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Wednesday, 7 February 2024
NON-CONFORMANCE VIC1 Region Wednesday, 7 February 2024
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: GLRWNSF1
Duration: 07/02/2024 14:00 to 07/02/2024 14:05
Amount: 103 MW
Constraint: NC-V_GLRWNSF1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024
Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.114399 is cancelled at 1945 hrs 06/02/2024.
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024
Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024
The actual LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 114397 has been updated at 1915 hrs 06/02/2024 to the following:
The Actual LOR1 condition is forecast to exist until 2000 hrs.
The forecast capacity reserve requirement is 1045 MW.
The minimum capacity reserve available is 950 MW.
Manager NEM Real Time Operations