[EventId:202402131900_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 13 February 2024 19:00
Issued by Australian Energy Market Operator Ltd at 1900 hrs on 13 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 February 2024.
Refer to market notice: 114659
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1900 hrs on 13 February 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202402131730_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 13 February 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 13 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1730 hrs on 13 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202402131630_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 13 February 2024 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 13 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 February 2024.
Refer to market notice: 114616
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1630 hrs on 13 February 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202402131630_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 13 February 2024 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 13 February 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 13 February 2024.
Refer to market notice: 114615
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1630 hrs on 13 February 2024.
This is an AEMO autogenerated Market Notice.
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.
Manager NEM Real Time Operations
[EventId:202402131450_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 13 February 2024 14:50
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 13 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 13 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1450 hrs on 13 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202402131450_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 13 February 2024 14:50
Issued by Australian Energy Market Operator Ltd at 1450 hrs on 13 February 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 13 February 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1450 hrs on 13 February 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Load Shedding Direction in the Vic Region
Load Shedding Direction in the Vic Region
AEMO has directed load shedding commencing at 1420 hrs 13/02/2024
in the Victoria region to restore power system security.
The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.
The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024
Manager NEM Real Time Operations