Market Notices

119137MARKET SYSTEMS21/10/2024 08:20:38 AM

CHG0098837 | Pre-Production | EMMS-Pre-Production Bay transfer for Core switch Refresh

Change Number: CHG0098837

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Electricity Market Management System_PreProd

Change Title: EMMS-Pre-Production Bay transfer for Core switch Refresh

Change Start Date & Time: 22/10/2024 07:00:00 AEST
Change End Date & Time: 22/10/2024 19:30:00 AEST
Outage Start Date & Time:
Outage End Date & Time:

Environment: Pre-Production

Participant Impact and Requirements: A Bay transfer is scheduled for 22nd October is not expected to have any impact. If any issues are identified because of this maintenance activity, please contact the AEMO Support Hub 1300 236 600.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
119036NON-CONFORMANCE18/10/2024 05:10:24 PM

NON-CONFORMANCE Region VIC1 Friday, 18 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 18 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BRYB2WF2
Duration: 18/10/2024 16:50 to 18/10/2024 17:10
Amount: 10 MW
Constraint: NC-V_BRYB2WF2

Auto-generated on behalf of Manager NEM Real Time Operations
     
119034NON-CONFORMANCE18/10/2024 04:55:17 PM

NON-CONFORMANCE Region SA1 Friday, 18 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Friday, 18 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: HPR1
Duration: 18/10/2024 16:40 to 18/10/2024 16:55
Amount: 22 MW
Constraint: NC-S_HPR1

Auto-generated on behalf of Manager NEM Real Time Operations
     
119021MARKET SYSTEMS18/10/2024 11:34:15 AM

CHG0099243 | Pre-Production | Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production

Change Number: CHG0099243

Notification issued to: Market Notice

Notification Type: Initial

Change Type: Normal

Service/ Component: Declared Wholesale Gas Market (DWGM)

Change Title: Maintenance activities to be performed on the Declared Wholesale Gas Market Systems Pre-Production.

Change Start Date & Time: 23/10/2024 07:00:23 AEST
Change End Date & Time: 23/10/2024 17:30:33 AEST
Outage Start Date & Time: 23/10/2024 08:00:00 AEST
Outage End Date & Time: 23/10/2024 12:30:00 AEST

Environment: Pre-Production

Participant Impact and Requirements: This is a regular procedure to allow routine maintenance. short service outages over the day for DWGM services, includiing MIBB and Web Exchanger.

Pre-Production Declared Wholesale Gas Market Systems (DWGM)

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
119020NON-CONFORMANCE18/10/2024 11:25:22 AM

NON-CONFORMANCE Region VIC1 Friday, 18 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 18 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BULBES1
Duration: 18/10/2024 11:05 to 18/10/2024 11:25
Amount: 20 MW
Constraint: NC-V_BULBES1

Auto-generated on behalf of Manager NEM Real Time Operations
     
119018MARKET SYSTEMS18/10/2024 08:38:58 AM

CHG0098658 | Completed | Production | Planned System Maintenance - Declared Wholesale Gas Market (DWGM)

Change Number: CHG0098658

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: DWGM - Web Exchanger

Change Title: Planned System Maintenance - Declared Wholesale Gas Market (DWGM)

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
118965NON-CONFORMANCE17/10/2024 07:35:25 AM

NON-CONFORMANCE Region VIC1 Thursday, 17 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Thursday, 17 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS4
Duration: 17/10/2024 07:25 to 17/10/2024 07:35
Amount: -53 MW
Constraint: NC-V_YWPS4

Auto-generated on behalf of Manager NEM Real Time Operations
     
118934MARKET SYSTEMS16/10/2024 03:56:26 PM

CHG0098812 | Completed | Pre-Production | Pre-Prod MSATS and eMDM November Maintenance Release

Change Number: CHG0098812

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Market Settlement & Transfer System

Change Title: Pre-Prod MSATS and eMDM November Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
118923NON-CONFORMANCE16/10/2024 07:35:21 AM

NON-CONFORMANCE Region QLD1 Wednesday, 16 October 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 16 October 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WOOLGSF1
Duration: 16/10/2024 06:55 to 16/10/2024 07:35
Amount: 112 MW
Constraint: NC-Q_WOOLGSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm