Market Notices

120075RESERVE NOTICE07/11/2024 12:27:24 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120059 is cancelled at 1100 hrs 07/11/2024.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
120066RESERVE NOTICE07/11/2024 11:45:12 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120061 is cancelled at 1145hrs 07/11/2024.

Manager NEM Real Time Operations
     
120061RESERVE NOTICE07/11/2024 10:52:29 AM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1800 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 658 MW.
The minimum capacity reserve available is 635 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
120059RESERVE NOTICE07/11/2024 11:13:20 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

1. From 1530 hrs to 1600 hrs 08/11/2024.
The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 760 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

AEMO Operations
     
120057RESERVE NOTICE07/11/2024 07:45:25 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120055 is cancelled at 0745 hrs 07/11/2024.

Manager NEM Real Time Operations
     
120055RESERVE NOTICE07/11/2024 06:15:21 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 07/11/2024 to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1394 MW.

Manager NEM Real Time Operations
     
120053RESERVE NOTICE07/11/2024 02:51:46 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120045 is cancelled at 0245 hrs 07/11/2024.

Manager NEM Real Time Operations
     
120052RESERVE NOTICE07/11/2024 02:49:06 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120050 has been updated at 0245 hrs to the following:

[1.] From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1112 MW.
The minimum capacity reserve available is 743 MW.

Manager NEM Real Time Operations
     
120051RESERVE NOTICE07/11/2024 02:46:44 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120047 is cancelled at 0245 hrs 07/11/2024.