Filter by category
Filter by Date
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120050 has been updated at 0245 hrs to the following:
[1.] From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1112 MW.
The minimum capacity reserve available is 743 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 1119967 has been updated at 0115 hrs to the following:
[1.] From 1730 hrs 07/11/2024 to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 1104 MW.
The minimum capacity reserve available is 722 MW.
[2.] From 1830 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1116 MW.
The minimum capacity reserve available is 801 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1293 MW.
Manager NEM Real Time Operations
Cancellation of Project Energy Connect (PEC-1) testing on 6th November 2024
Refer to market notice 119963
The Project Energy Connect (PEC-1) testing on 6th November has now been cancelled.
Terry Liu
AEMO Operations
Forecast Minimum System Load 1 (MSL1) condition in the VIC region on 10/11/2024
Update to Market Notice 119920 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1745 MW
o MSL2 - 1245 MW
o MSL3 - 745 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1230 hrs to 1330 hrs 10/11/2024. Minimum regional demand is forecast to be 1719 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 09/11/2024
Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 06/11/2024.
Refer to Market Notice 119866 for Forecast MSL1.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119918 is cancelled at 1400 hrs 06/11/2024
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1112 MW.
The minimum capacity reserve available is 886 MW.
Manager NEM Real Time Operations
Correction to testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions
Refer to market notice 119961
This is correction to Project Energy Connect (PEC-1) testing time issued in previous notice 119961.
Testing time is on 6th November from 11:00 hrs to 22:00 hrs.
The test is for flows in both directions up to 50 MW. This test includes a trip and reclose of a line in South Australia. Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.
Mya San
AEMO Operations