PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 06/11/2024 to 1830 hrs 06/11/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 1086 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119927 has been updated at 0430 hrs to the following:
[1.] From 1800 hrs 06/11/2024 to 1830 hrs 06/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1312 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119911 has been updated at 1700 hrs to the following:
[1.] From 1800 hrs 06/11/2024 to 1830 hrs 06/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1278 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 05/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119913 is cancelled at 1650 hrs 05/11/2024.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 119868 has been updated at 1400 hrs 05/11/2024 to the following:
From 1700 hrs to 1930 hrs 07/11/2024.
The forecast capacity reserve requirement is 1002 MW.
The minimum capacity reserve available is 906 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119871 has been updated at 1400 hrs 05/11/2024 to the following:
From 1730 hrs to 1800 hrs 08/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1369 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119870 has been updated at 1400 hrs 05/11/2024 to the following:
1. From 1100 hrs to 1130 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1366 MW.
2. From 1200 hrs to 1230 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1183 MW.
3. From 1800 hrs to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1123 MW.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1800 hrs 06/11/2024 to 1830 hrs 06/11/2024.
The forecast capacity reserve requirement is 1108 MW.
The minimum capacity reserve available is 949 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Periods:
[1.] From 1700 hrs 06/11/2024 to 1730 hrs 06/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1137 MW.
[2.] From 1830 hrs 06/11/2024 to 1900 hrs 06/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1093 MW.