Reclassification of a Non-Credible Contingency Event: Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line in VIC due to lightning.
Reclassification of a non-credible contingency event as a credible contingency event due to lightning.
AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: VIC
Lines: Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line
Duration: 06/11/2024 12:15 hrs until further notice
Constraint set(s) invoked: V-ROYP78_R_N-2
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: TAS1
Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV
Cancellation time: 06/11/2024 09:24
Constraint set(s) revoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Refer AEMO Electricity Market Notice 119943
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Tungatinah-Lake Echo-Waddamana 1 110kV line and Tungatinah-Waddamana 2 110kV line in TAS1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: TAS1
Lines: Tungatinah-Lake Echo-Waddamana 1 110kV and Tungatinah-Waddamana 2 110kV
Duration: 06/11/2024 08:21 until further notice
Constraint set(s) invoked:
T-TUWA12_110_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 05/11/2024 18:24
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 119916
Auto-generated on behalf of Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 05/11/2024 14:22 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 04/11/2024 20:29
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 119864
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 04/11/2024
Cancellation of Actual (LOR1) condition in the QLD region - 04/11/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.119882 is cancelled at 1900 hrs 04/11/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 04/11/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1135 MW
The minimum capacity reserve available is 875 MW
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Duration: 04/11/2024 14:27 until further notice
Constraint set(s) invoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Auto-generated on behalf of Manager NEM Real Time Operations