Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120045 is cancelled at 0245 hrs 07/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120050 has been updated at 0245 hrs to the following:
[1.] From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1112 MW.
The minimum capacity reserve available is 743 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 1119967 has been updated at 0115 hrs to the following:
[1.] From 1730 hrs 07/11/2024 to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 1104 MW.
The minimum capacity reserve available is 722 MW.
[2.] From 1830 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1116 MW.
The minimum capacity reserve available is 801 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1293 MW.
Manager NEM Real Time Operations
[EventId:202411061520_NRM_SA1_VIC1_stopped] NEGRES CONSTRAINT NRM_SA1_VIC1 ceased operating from 06 November 2024 15:20
Issued by Australian Energy Market Operator Ltd at 1520 hrs on 6 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.
Refer to market notice: 119986
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the SA to VIC directional interconnector.
The negative residue constraint NRM_SA1_VIC1 ceased operating at 1520 hrs on 6 November 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202411061445_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 06 November 2024 14:45
Issued by Australian Energy Market Operator Ltd at 1445 hrs on 6 November 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 6 November 2024.
Refer to market notice: 119973
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1445 hrs on 6 November 2024.
This is an AEMO autogenerated Market Notice.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119918 is cancelled at 1400 hrs 06/11/2024
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
[EventId:202411061435_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 06 November 2024 14:35
Issued by Australian Energy Market Operator Ltd at 1435 hrs on 6 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.
The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1435 hrs on 6 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202411061405_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 06 November 2024 14:05
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 6 November 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 6 November 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.
The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1405 hrs on 6 November 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.