Market Notices

115196RECALL GEN CAPACITY27/02/2024 08:27:52 AM

Request for Generator Recall Information for 29/02/2024 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 115193. Additional generation in QLD could assist in alleviating the forecast LOR2 condition in NSW.

Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
115195RECALL GEN CAPACITY27/02/2024 08:26:49 AM

Request for Generator Recall Information for 29/02/2024 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 115193.

Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
115152RESERVE NOTICE26/02/2024 04:19:36 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115148 has been updated at 1615 hrs to the following:

[1.] From 1800 hrs 26/02/2024 to 1900 hrs 26/02/2024.
The forecast capacity reserve requirement is 1155 MW.
The minimum capacity reserve available is 827 MW.

Manager NEM Real Time Operations
115148RESERVE NOTICE26/02/2024 02:47:47 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1800 hrs 26/02/2024 to 1900 hrs 26/02/2024.
The forecast capacity reserve requirement is 1124 MW.
The minimum capacity reserve available is 974 MW.


Manager NEM Real Time Operations
115147RESERVE NOTICE26/02/2024 03:24:09 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115113 has been updated at 1400 hrs 26/02/2024 to the following:

1. From 1430 hrs to 1630 hrs 29/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 685 MW.

2. From 1930 hrs to 2130 hrs 29/02/2024.
The forecast capacity reserve requirement is 1735 MW.
The minimum capacity reserve available is 1050 MW.

AEMO Operations
115145RESERVE NOTICE26/02/2024 03:23:09 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/02/2024

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115114 has been updated at 1400 hrs 26/02/2024 to the following:

From 1700 hrs to 2030 hrs 29/02/2024.
The forecast capacity reserve requirement is 1259 MW.
The minimum capacity reserve available is 729 MW.

AEMO Operations
115114RESERVE NOTICE25/02/2024 02:32:31 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115087 has been updated at 1430 hrs 25/02/2024 to the following:

[1.] From 1800 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 1255 MW.
The minimum capacity reserve available is 1152 MW.

Manager NEM Real Time Operations
115113RESERVE NOTICE25/02/2024 02:31:26 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115086 has been updated at 1430 hrs 25/02/2024 to the following:

[1.] From 1500 hrs 29/02/2024 to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 1402 MW.
The minimum capacity reserve available is 725 MW.


Manager NEM Real Time Operations
115087RESERVE NOTICE24/02/2024 02:45:51 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115039 has been updated at 1445 hrs 24/02/2024 to the following:

[1.] From 1730 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 915 MW.

Manager NEM Real Time Operations