114118RESERVE NOTICE01/02/2024 03:30:36 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114070 has been updated at 1400 hrs 01/02/2024 to the following:

From 1300 hrs to 2000 hrs 06/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.

AEMO Operations
114117RESERVE NOTICE01/02/2024 03:29:42 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114075 has been updated at 1400 hrs 01/02/2024 to the following:

From 1230 hrs to 2130 hrs 05/02/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 685 MW.

AEMO Operations
114116RESERVE NOTICE01/02/2024 03:28:54 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114068 has been updated at 1400 hrs 01/02/2024 to the following:

From 1800 hrs to 1930 hrs 06/02/2024.
The forecast capacity reserve requirement is 1264 MW.
The minimum capacity reserve available is 944 MW.

AEMO Operations
114115RESERVE NOTICE01/02/2024 03:27:56 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1830 hrs to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1267 MW.
The minimum capacity reserve available is 1151 MW.

AEMO Operations
114076RESERVE NOTICE31/01/2024 03:27:45 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114017 is cancelled at 1400 hrs 31/01/2024.

AEMO Operations
114075RESERVE NOTICE31/01/2024 03:28:35 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114019 has been updated at 1400 hrs 31/01/2024 to the following:

1. From 1400 hrs to 1630 hrs 05/02/2024.
The forecast capacity reserve requirement is 1462 MW.
The minimum capacity reserve available is 905 MW.

2. From 1700 hrs to 2000 hrs 05/02/2024.
The forecast capacity reserve requirement is 1460 MW.
The minimum capacity reserve available is 995 MW.

AEMO Operations
114070RESERVE NOTICE31/01/2024 03:25:43 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114021 has been updated at 1400 hrs 31/01/2024 to the following:

1. From 1400 hrs to 1730 hrs 06/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 813 MW.

2. From 1900 hrs to 2100 hrs 06/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 892 MW.

AEMO Operations
114069RESERVE NOTICE31/01/2024 03:26:40 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114023 is cancelled at 1400 hrs 31/01/2024.

AEMO Operations
114068RESERVE NOTICE31/01/2024 03:24:39 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 114024 has been updated at 1400 hrs 31/01/2024 to the following:

From 1730 hrs to 2000 hrs 06/02/2024.
The forecast capacity reserve requirement is 1267 MW.
The minimum capacity reserve available is 944 MW.