STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113740 has been updated at 1600 hrs to the following:
From 1730 hrs 27/01/2024 to 2000 hrs 27/01/2024.
The forecast capacity reserve requirement is 731 MW.
The minimum capacity reserve available is 655 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113732 has been updated at 1300 hrs to the following:
From 1700 hrs to 2030 hrs 27/01/2024.
The forecast capacity reserve requirement is 766 MW.
The minimum capacity reserve available is 681 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113730 has been updated at 1100 hrs to the following:
1. From 1730 hrs to 2000 hrs 27/01/2024.
The forecast capacity reserve requirement is 743 MW.
The minimum capacity reserve available is 708 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113722 has been updated at 1000 hrs to the following:
1. From 1730 hrs to 1830 hrs 27/01/2024.
The forecast capacity reserve requirement is 740 MW.
The minimum capacity reserve available is 735 MW.
2. From 1900 hrs to 1930 hrs 27/01/2024.
The forecast capacity reserve requirement is 736 MW.
The minimum capacity reserve available is 734 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 26/01/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113711 is cancelled at 0800 hrs 25/01/2024.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 113714 has been updated at 0430 hrs to the following:
[1.] From 1730 hrs 27/01/2024 to 2000 hrs 27/01/2024.
The forecast capacity reserve requirement is 714 MW.
The minimum capacity reserve available is 573 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/01/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 113715 is cancelled at 2155 hrs 24/01/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 25/01/2024 to 1700 hrs 25/01/2024.
The forecast capacity reserve requirement is 936 MW.
The minimum capacity reserve available is 912 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 27/01/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period[s]:
[1.] From 1800 hrs 27/01/2024 to 1930 hrs 27/01/2024.
The forecast capacity reserve requirement is 714 MW.
The minimum capacity reserve available is 636 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.