114698MARKET SYSTEMS14/02/2024 09:54:49 AM

INC0126874 | Overnight standing data updates not reflecting in MSATS Enterprise MDM

AEMO ELECTRICITY MARKET NOTICE
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to the Market Settlement & Transfer Solution Enterprise MDM service.
The overnight MSATS CATS change requests are not reflected in the MSATS Enterprise MDM. This has also impacted the Meter Data ingestion.
MDPs are advised to not resend meter data files until advised or resolved notification for this incident has been received.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
114589RESERVE NOTICE13/02/2024 01:52:07 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:

[1.] From 1430 hrs 13/02/2024 to 1600 hrs 13/02/2024.
The forecast capacity reserve requirement is 562 MW.
The minimum capacity reserve available is 384 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
114531RESERVE NOTICE12/02/2024 02:47:22 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114528 is cancelled at 1445 hrs 12/02/2024.

Manager NEM Real Time Operations
114528RESERVE NOTICE12/02/2024 12:50:49 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1700 hrs 13/02/2024 to 1830 hrs 13/02/2024.
The forecast capacity reserve requirement is 1224 MW.
The minimum capacity reserve available is 1098 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
114518RESERVE NOTICE12/02/2024 03:11:37 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114503 is cancelled at 0300 hrs 12/02/2024

[No LOR2 condition is currently forecast in the STPASA period.]

Manager NEM RTO
114503RESERVE NOTICE11/02/2024 02:37:42 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114495 has been updated at 1430 hrs 11/02/2024 to the following:

[1.] From 1600 hrs 13/02/2024 to 1630 hrs 13/02/2024.
The forecast capacity reserve requirement is 1211 MW.
The minimum capacity reserve available is 1122 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
114495RESERVE NOTICE11/02/2024 07:32:26 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

[1.] From 1600 hrs 13/02/2024 to 1700 hrs 13/02/2024.
The forecast capacity reserve requirement is 1319 MW.
The minimum capacity reserve available is 1056 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
114459MARKET SYSTEMS09/02/2024 03:04:19 PM

CHG0083624 | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Number: CHG0083624
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Gas Hub

Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.

Change Start Date & Time: 18/02/2024 09:00:00 AEST
Change End Date & Time: 18/02/2024 17:00:00 AEST
Outage Start Date & Time:
Outage End Date & Time:
Environment: Production

Participant Impact and Requirements: The following impacts are expected during this maintenance:
- All access to the Electricity B2B Hub will be unavailable.
- All access to the Gas B2B Hub and all ebXML gateways (AEMOMIBB, AGNLGWY, LVI & VENCORP) will be unavailable. CATS and MDMT transactions for VIC/QLD will be delayed during the maintenance window.
- Users are not required to take any action due to this change, however will need to enact manual workarounds for the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
114375MARKET SYSTEMS06/02/2024 02:01:20 PM

CHG0082609 | Production | MSATS-CATS Production Maintenance

Change Number: CHG0082609
Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS-CATS Production Maintenance
Change Start Date & Time: 18/02/2024 09:00:00 AEST
Change End Date & Time: 18/02/2024 17:00:00 AEST
Outage Start Date & Time: 18/02/2024 10:00:00 AEST
Outage End Date & Time: 18/02/2024 14:00:00 AEST

Environment: Production

The change has some login outages that are below and will impact participants logging into the web portal for MSATS, OPDMS, NOS and EMMS production environments.
AEMO recommends users who need to use these AEMO services, login prior to the start of the outage and remain logged in.
NOTE: If you log out of this session, you will be unable to log back in until the completion of the outage.
A URM outage will occur between 11:00 - 11:30 AEST and have an expected outage duration of upto 15 minutes. During this time users will not be able to have new login sessions into TMM, OPDMS, NOS or EMMS WebPortal.

The MSATS outage is 10:00 - 14:00 AEST which is the agreed maintenance window.
Participants should be aware that: MSATS, Meter data processing, RM reports, B2B, B2M screen, NMI Discovery, CDR, CDP will not be available Participant passwords will be retained. Users that log out and users that try to log in once the URM outage has commenced will only be able to log in after URM outage is complete. Any password resets or new account creations completed during the URM outage window will need to be redone MSATS FTP sessions will be disabled during outage Wholesale MMS FTP will still be available .

The redirection menu will be unavailable during the MSATS outage timeframe Report any impacts to the AEMO Information and Support Hub or call 1300 236 648.
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm