Filter by category
Filter by Date
Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 14/03/2024
Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 14/03/2024
At 0800 hrs 14/03/2024 there was a short notice outage of Lismore 132kV SVC.
The following constraint set(s) invoked at 0800 hrs 14/03/2024
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1930 hrs 11/03/2024 to 2030 hrs 11/03/2024.
The forecast capacity reserve requirement is 469 MW.
The minimum capacity reserve available is 402 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115588 is cancelled at 0717 hrs 11/03/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115587 has been updated at 0520 hrs to the following:
[1.] From 1930 hrs 11/03/2024 to 2000 hrs 11/03/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 545 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 11/03/2024 to 1900 hrs 11/03/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 546 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115573 is cancelled at 1845 hrs 10/03/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1830 hrs 11/03/2024 to 1900 hrs 11/03/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 586 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 14/03/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115552 is cancelled at 1445 hrs 10/03/2024.
No LOR condition is currently forecast in the NSW region in the STPASA period.
Manager NEM RTO
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 10/03/2024
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 115569 is cancelled at 2310 hrs 09/03/2024.
Manager NEM Real Time Operations