Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS
Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS
Refer to Market Notice 117942
Direction is cancelled from: 1330 hrs 29/08/2024
Manager NEM Real Time Operations
Direction - SA region 29/08/2024
Direction - SA region 29/08/2024
Refer to Market Notice 117813
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS at 1300 hrs 29/08/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 1300 hrs 29/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1330 hrs 29/08/2024 / further notice.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Market Notice 117929
The TORRB3 TORRENS ISLAN direction is now expected to synhronise at 1330 hrs 29/08/2024.
The direction update is issued at 1710 hrs 28/08/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 117919
Direction is cancelled from: 1800 hrs 28/08/2024
Manager NEM Real Time Operations
Direction - SA region 26/08/2024
Direction - SA region 26/08/2024
Refer to Market Notice 117813
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN at 1600 hrs 28/08/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 1200 hrs 29/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 30/08/2024.
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Market Notice 117892
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 30/08/2024.
The direction update is issued at 1548 hrs 28/08/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Market Notice 117894
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1800 hrs 28/08/2024.
The direction update is issued at 1000 hrs 28/08/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Market Notice 117812
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1830 hrs 28/08/2024.
The direction update is issued at 1600 hrs 27/08/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer AEMO Electricity Market Notice 117811
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 0400 hrs 29/08/2024.
The direction update is issued at 1600 hrs 27/08/2024.
Manager NEM Real Time Operations