119994SETTLEMENTS RESIDUE06/11/2024 02:47:19 PM

[EventId:202411061445_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 06 November 2024 14:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1445 hrs on 6 November 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 6 November 2024.

Refer to market notice: 119973

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.

The negative residue constraint NRM_VIC1_NSW1 ceased operating at 1445 hrs on 6 November 2024.

This is an AEMO autogenerated Market Notice.
     
119986SETTLEMENTS RESIDUE06/11/2024 02:36:33 PM

[EventId:202411061435_NRM_SA1_VIC1_started] NEGRES CONSTRAINT NRM_SA1_VIC1 started operating from 06 November 2024 14:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1435 hrs on 6 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - SA to VIC - 6 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the SA to VIC directional interconnector.

The negative residue constraint set NRM_SA1_VIC1 commenced operating from 1435 hrs on 6 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119979MARKET INTERVENTION06/11/2024 06:09:53 PM

Cancellation - AEMO Intervention Event - SA region 04/11/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 04/11/2024

Refer to Market Notice 119875

The AEMO Intervention Event and all associated directions are cancelled from 1800 hrs on 06/11/2024.


Manager NEM Real Time Operations
     
119977MARKET INTERVENTION06/11/2024 05:03:39 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 119875

Direction is cancelled from: 1700 hrs 06/11/2024

Manager NEM Real Time Operations
     
119975MARKET INTERVENTION06/11/2024 04:00:29 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN

Refer to Market Notice 119875

Direction is cancelled from: 1600 hrs 06/11/2024

Manager NEM Real Time Operations
     
119973SETTLEMENTS RESIDUE06/11/2024 02:05:18 PM

[EventId:202411061405_NRM_VIC1_NSW1_started] NEGRES CONSTRAINT NRM_VIC1_NSW1 started operating from 06 November 2024 14:05

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1405 hrs on 6 November 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 6 November 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to NSW directional interconnector.

The negative residue constraint set NRM_VIC1_NSW1 commenced operating from 1405 hrs on 6 November 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
119966MARKET INTERVENTION06/11/2024 01:19:39 PM

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO ELECTRICITY MARKET NOTICE

Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region

AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0730 hrs 07/11/2024.

The foreseeable circumstance requiring the need for intervention is Voltage.

Manager NEM Real Time Operations
     
119963GENERAL NOTICE06/11/2024 11:27:15 AM

Correction to testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119961

This is correction to Project Energy Connect (PEC-1) testing time issued in previous notice 119961.
Testing time is on 6th November from 11:00 hrs to 22:00 hrs.

The test is for flows in both directions up to 50 MW. This test includes a trip and reclose of a line in South Australia. Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Mya San
AEMO Operations
     
119961GENERAL NOTICE06/11/2024 10:03:46 AM

Revised testing time for Project Energy Connect (PEC-1) 6th November 2024 for flows in both directions

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119901

The Project Energy Connect (PEC-1) testing opportunity has changed ans it is now on 6th November at 22:00 hrs.

The test is for flows in both directions up to 50 MW.

This test includes a trip and reclose of a line in South Australia.

Please also refer to the published formal PEC Stage 1 and HIC capacity release testing information at the following link https://aemo.com.au/-/media/files/stakeholder_consultation/consultations/nem-consultations/2023/project-energyconnect-stage-1-and-hic-capacity-release/pec-stage-1-and-hic---final-test-program.pdf?la=en.

Terry Liu
AEMO Operations
     