PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120047 is cancelled at 0245 hrs 07/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 1119967 has been updated at 0115 hrs to the following:
[1.] From 1730 hrs 07/11/2024 to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 1104 MW.
The minimum capacity reserve available is 722 MW.
[2.] From 1830 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1116 MW.
The minimum capacity reserve available is 801 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120044 has been updated at 0100 hrs to the following:
[1.] From 1800 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 702 MW.
The minimum capacity reserve available is 684 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1293 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 747 MW.
The minimum capacity reserve available is 589 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Forecast Minimum System Load 1 (MSL1) condition in the VIC region on 10/11/2024
Update to Market Notice 119920 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
o MSL1 - 1745 MW
o MSL2 - 1245 MW
o MSL3 - 745 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1230 hrs to 1330 hrs 10/11/2024. Minimum regional demand is forecast to be 1719 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO Operations
Cancellation - Forecast Minimum System Load 1 (MSL1) condition in the VIC Region on 09/11/2024
Cancellation - Forecast MSL1 - VIC Region at 1400 hrs 06/11/2024.
Refer to Market Notice 119866 for Forecast MSL1.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/11/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 119918 is cancelled at 1400 hrs 06/11/2024
No LOR condition is currently forecast in the STPASA period.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1112 MW.
The minimum capacity reserve available is 886 MW.
Manager NEM Real Time Operations