Update to system strength constraints in North Queensland
Refer to market notice 110677
AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of new feeder 8905 (H13 Ross - H39 Woree) 275kV line in Far North Queensland, the system normal system strength equations for low North Queensland demands and all Karreya stations out of service conditions have been revised.
A revision to the constraint equations will be implemented at 1400 hrs on Tuesday 20th February 2024.
The new system strength combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice
This advice contains all the combinations for Queensland for system normal cases.
Below constraint equations in the Q-NIL set will be modified:
- Q_NIL_STRGTH_KBWF
- Q_NIL_STRGTH_KBWF_I
- Q_NIL_STRGTH_HAUSF
- Q_NIL_STRGTH_HAUSF_I
- Q_NIL_STRGTH_MEWF
- Q_NIL_STRGTH_MEWF_I
AEMO Operations
CHG0083624 | Completed | Production | A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: A production site transfer of the Electricity and Gas B2B Hub will be carried out to facilitate maintenance activities.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 114838 is cancelled at 1430 hrs 18/02/2024.
No LOR condition is currently forecast in the STPASA period.
Manager NEM RTO
CHG0082609 | Completed | Production | MSATS-CATS Production Maintenance
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)
Change Title: MSATS-CATS Production Maintenance
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1630 hrs 23/02/2024 to 1700 hrs 23/02/2024.
The forecast capacity reserve requirement is 1637 MW.
The minimum capacity reserve available is 1594 MW.
Manager NEM Real Time Operations
[EventId:202402131320_confirmed] Prices for interval 13-Feb-2024 13:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1452 hrs on 14 February 2024
PRICES ARE NOW CONFIRMED for trading interval 13-Feb-2024 13:20.
In accordance with Market Notice 114583 AEMO has reviewed this trading interval and determined that:
- Manifestly Incorrect Inputs did not apply
- Over-Constrained Dispatch has been resolved for dispatch interval
Changed Prices ($/MWh)
TYPE
Region Original Adjusted
Price Price
ENERGY
NSW1 -$38.41 -$35.04
QLD1 -$40.60 -$36.57
LOWERREG
TAS1 $16,600.00 $9.88
RAISEREG
TAS1 $16,600.00 $150.68
This is an AEMO autogenerated Market Notice.
INC0126874 | RESOLVED | Overnight standing data updates not reflecting in MSATS Enterprise MDM
SERVICE INTERRUPTION - RESOLVED
The issue with the standing data updates not reflecting in MSATS Enterprise MDM has been resolved.
There are no further steps to be completed. The service is now fully restored, and no further communication will be released unless there is a change of status.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
CHG0082504 | Completed | Pre-Production | Removal of support of TLS Version 1.1 and lower
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: Removal of support of TLS Version 1.1 and lower
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
INC0126874 | Overnight standing data updates not reflecting in MSATS Enterprise MDM
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to the Market Settlement & Transfer Solution Enterprise MDM service.
The overnight MSATS CATS change requests are not reflected in the MSATS Enterprise MDM. This has also impacted the Meter Data ingestion.
MDPs are advised to not resend meter data files until advised or resolved notification for this incident has been received.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager