Filter by category
Filter by Date
CHG0087932 | Pre-Production | Planned System Maintenance in Preproduction for Web Exchanger
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: DWGM - Web Exchanger
Change Title: Planned System Maintenance in Preproduction for Web Exchanger
Change Start Date & Time: 28/03/2024 10:00:00 AEST
Change End Date & Time: 28/03/2024 17:00:00 AEST
Outage Start Date & Time: 28/03/2024 14:00:00 AEST
Outage End Date & Time: 28/03/2024 15:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: Access to WEX will not be available during outage window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0087908 | Pre-Production | Pre-Prod MSATS Lifecycle Maintenance
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)_PreProd
Change Title: Pre-Prod MSATS Lifecycle Maintenance
Change Start Date & Time: 27/03/2024 19:00:00 AEST
Change End Date & Time: 01/04/2024 20:00:00 AEST
Outage Start Date & Time: 27/03/2024 19:00:00 AEST
Outage End Date & Time: 01/04/2024 21:18:14 AEST
Environment: Pre-Production
Participant Impact and Requirements: MSATS (preprod), CDR (preprod) and CDP (preprod) will be unavailable daily from today 27th March between 19:00 - 20:00 Market Time (AEST) until Monday 1st April
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0086100 | Completed | Production | Planned System Maintenance - Declared Wholesale Gas Market (DWGM)
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Declared Wholesale Gas Market
Change Title: Planned System Maintenance - Declared Wholesale Gas Market (DWGM)
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0087317 | Completed | Pre-Production | Pre-Prod BAU Retail November Maintenance Release
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Pre-Prod BAU Retail November Maintenance Release
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0087653 | Production | Prod eMDM Maintenance
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MDM - Meter Data Management
Change Title: Prod eMDM Maintenance
Change Start Date & Time: 07/04/2024 10:00:00 AEST
Change End Date & Time: 07/04/2024 17:00:00 AEST
Outage Start Date & Time: 07/04/2024 10:00:00 AEST
Outage End Date & Time: 07/04/2024 14:00:00 AEST
Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.
Meter data processing and RM reports will not be available during the outage period.
User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.
MSATS B2B Transactions and B2B MSATS Screens will be unavailable during this outage
NMI Discovery will not be available during the outage period.
CDR and CDP will not be available during the outage period.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0087775 | Pre-Production | Pre-Prod MSATS Lifecycle Maintenance
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)_PreProd
Change Title: Pre-Prod MSATS Lifecycle Maintenance
Change Start Date & Time: 02/04/2024 12:00:00 AEST
Change End Date & Time: 02/04/2024 23:30:00 AEST
Outage Start Date & Time: 02/04/2024 12:00:00 AEST
Outage End Date & Time: 02/04/2024 22:00:00 AEST
Environment: Pre-Production
Participant Impact and Requirements: MSATS (preprod), CDR (preprod) and CDP (preprod) will be unavailble on the 2nd April 12:00pm AEST to 10:00pm AEST
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
CHG0087752 | Completed | Pre-Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Short Term Trading Market
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0087184 | Completed | Pre-Production | Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Short Term Trading Market
Change Title: Maintenance activities to be performed on the Gas Short Term Trading Market Systems Pre-Production.
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
CHG0086184 | Production | NSW Internet Router Refresh
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: Local Area Network
Change Title: NSW Internet Router Refresh
Change Start Date & Time: 06/04/2024 09:00:45 AEST
Change End Date & Time: 06/04/2024 14:00:45 AEST
Outage Start Date & Time: 06/04/2024 09:30:00 AEST
Outage End Date & Time: 06/04/2024 13:30:00 AEST
Environment: Production
Participant Impact and Requirements: The following impacts are expected to participant connectivity during this planned outage:
IPWAN Participants - Nil
Lan-2-Lan VPN Participants (IPSEC) - Up to 2 hour outage for participants who have established their VPN connection/s via the AEMO NSW datacenter termination point (202.44.78.10) only - All L2L connections should be established to both QLD / NSW.
Note: Participants are encouraged to ensure their VPN connections are already established or are configured (as per AEMO best practice) to automatically failover to the alternate AEMO QLD datacenter termination point (202.44.76.10) prior to this scheduled outage.
B2B VPN - Up to 2 hour outage to TNSPs with B2B VPN to AEMO NSW Datacentre if VPN connection is only terminating in NSW only
SSL VPN Participants: None expected as DNS entry will be updated to remove NSW IP.
GASHUB: No impact is expected as GASHUB is currently operating out of BNE Datacenter.
Other Impacts will have been communicated in advance.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .