114237RESERVE NOTICE04/02/2024 01:09:16 PM

PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1430 hrs 05/02/2024 to 1800 hrs 05/02/2024.
The forecast capacity reserve requirement is 1184 MW.
The minimum capacity reserve available is 762 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
114232NON-CONFORMANCE04/02/2024 11:45:17 AM

NON-CONFORMANCE Region NSW1 Sunday, 4 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Sunday, 4 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: SEBSF1
Duration: 04/02/2024 11:05 to 04/02/2024 11:45
Amount: 35 MW
Constraint: NC-N_SEBSF1

Auto-generated on behalf of Manager NEM Real Time Operations
114229RESERVE NOTICE04/02/2024 10:56:33 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114228 has been updated at 1045 hrs 04/02/2024 to the following:

[1.] From 1530 hrs 05/02/2024 to 1730 hrs 05/02/2024.
The forecast capacity reserve requirement is 1185 MW.
The minimum capacity reserve available is 1135 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
114228RESERVE NOTICE04/02/2024 08:07:18 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114227 has been updated at 0800 hrs 04/02/2024 to the following:

[1.] From 1300 hrs 05/02/2024 to 2000 hrs 05/02/2024.
The forecast capacity reserve requirement is 1161 MW.
The minimum capacity reserve available is 700 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
114227RESERVE NOTICE03/02/2024 11:36:16 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114223 has been updated at 2330 hrs 03/02/2024 to the following:

[1.] From 1330 hrs 05/02/2024 to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1058 MW.
The minimum capacity reserve available is 754 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
114223RESERVE NOTICE03/02/2024 06:37:31 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114213 has been updated at 1830 hrs 03/02/2024 to the following:

[1.] From 1400 hrs 05/02/2024 to 1930 hrs 05/02/2024.
The forecast capacity reserve requirement is 1383 MW.
The minimum capacity reserve available is 782 MW.

[2.] From 2000 hrs 05/02/2024 to 2030 hrs 05/02/2024.
The forecast capacity reserve requirement is 1183 MW.
The minimum capacity reserve available is 1107 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
114213RESERVE NOTICE03/02/2024 02:41:49 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114193 has been updated at 1400 hrs 03/02/2024 to the following:

[1.] From 1230 hrs 05/02/2024 to 1730 hrs 05/02/2024.
The forecast capacity reserve requirement is 1246 MW.
The minimum capacity reserve available is 685 MW.

[2.] From 1830 hrs 05/02/2024 to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1231 MW.
The minimum capacity reserve available is 1048 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
114210NON-CONFORMANCE03/02/2024 02:35:17 PM

NON-CONFORMANCE Region QLD1 Saturday, 3 February 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 3 February 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 03/02/2024 14:25 to 03/02/2024 14:35
Amount: -19 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
114206RESERVE NOTICE03/02/2024 02:19:47 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114201 is cancelled at 1400 hrs 03/02/2024.

Manager NEM Real Time Operations
X