Market Notices

114017RESERVE NOTICE30/01/2024 03:17:27 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113976 has been updated at 1400 hrs 30/01/2024 to the following:

From 1700 hrs to 1930 hrs 04/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1174 MW.

AEMO Operations
114012MARKET SYSTEMS30/01/2024 01:47:21 PM

CHG0082787 | Completed | Pre-Production | Pre-Production MSATS r50.0.5 Patch Release

Change Number: CHG0082787

Notification issued to: Market Notice

Notification Type: Completed

Change Type: Normal

Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: Pre-Production MSATS r50.0.5 Patch Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
113998RESERVE NOTICE29/01/2024 08:23:46 PM

Cancellation of Actual (LOR1) condition in the QLD region - 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 29/01/2024

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.113994 is cancelled at 2000 hrs 29/01/2024.

Manager NEM Real Time Operations
113994RESERVE NOTICE29/01/2024 06:12:37 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 29/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1810 hrs.

The Actual LOR1 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 1197 MW.
The minimum capacity reserve available is 1026 MW.

Manager NEM Real Time Operations
113979RESERVE NOTICE29/01/2024 03:22:26 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1830 hrs to 1900 hrs 05/02/2024.
The forecast capacity reserve requirement is 1254 MW.
The minimum capacity reserve available is 1187 MW.

AEMO Operations
113978RESERVE NOTICE29/01/2024 03:13:45 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1430 hrs to 2200 hrs 05/02/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 730 MW.

AEMO Operations
113976RESERVE NOTICE29/01/2024 03:10:28 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113912 has been updated at 1400 hrs 29/01/2024 to the following:

From 1700 hrs to 2130 hrs 04/02/2024.
The forecast capacity reserve requirement is 1489 MW.
The minimum capacity reserve available is 1108 MW.

AEMO Operations
113966RESERVE NOTICE29/01/2024 11:07:25 AM

PDPASA - Update to Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

Refer to MN 113962

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1730 hrs 29/01/2024 to 1930 hrs 29/01/2024.
The forecast capacity reserve requirement is 1106 MW.
The minimum capacity reserve available is 965 MW.


Manager NEM Real Time Operations
113962RESERVE NOTICE29/01/2024 09:52:11 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:

[1.] From 1830 hrs 29/01/2024 to 1900 hrs 29/01/2024.
The forecast capacity reserve requirement is 1035 MW.
The minimum capacity reserve available is 928 MW.