Filter by category
Filter by Date
CHG0082504 | Completed | Pre-Production | Removal of support of TLS Version 1.1 and lower
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Business to Business data exchange
Change Title: Removal of support of TLS Version 1.1 and lower
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
NEM Local Temperature Alerts for SA, VIC from 14 Feb 2024 to 18 Feb 2024
AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.
SA
Port Augusta Ap (39+ Deg C): 17th Feb, 18th Feb
VIC
Mildura Ap (39+ Deg C): 18th Feb
The NEM Local Temperature Alert Levels are:
Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.
AEMO requests Market Participants to:
1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,
2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.
Further information is available at:
https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts
AEMO Operations Planning
INC0126874 | Overnight standing data updates not reflecting in MSATS Enterprise MDM
SERVICE INTERRUPTION - ALERT
AEMO is experiencing a service interruption relating to the Market Settlement & Transfer Solution Enterprise MDM service.
The overnight MSATS CATS change requests are not reflected in the MSATS Enterprise MDM. This has also impacted the Meter Data ingestion.
MDPs are advised to not resend meter data files until advised or resolved notification for this incident has been received.
For further enquiries please contact the AEMO Support Hub
Phone: 1300 236 600
Email: supporthub@aemo.com.au
AEMO IT Duty Manager
Load Restoration Direction Cancellation in the Vic Region
Cancellation - Load Restoration Direction in the Vic Region - 13/02/2024
Refer to AEMO Electricity Market Notice ID 114607
Load restoration as directed is complete. Direction cancelled from 1510 hrs 13/02/2024.
Manager NEM Real Time Operations
Load Restoration Direction in the Vic Region
Load Restoration Direction in the Vic Region
AEMO has directed load restoration commencing at 1450 hrs 13/02/2024 in the Victoria region
The direction was issued under section 116 of the NEL, and was a clause 4.8.9 instruction under the NER.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the VIC Region on 13/02/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 1430 hrs 13/02/2024 to 1600 hrs 13/02/2024.
The forecast capacity reserve requirement is 562 MW.
The minimum capacity reserve available is 384 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Variation to FCAS regulation raise requirements: NEM Mainland - 13/02/2024
Variation to FCAS regulation raise requirements: NEM Mainland - 13/02/2024
FCAS Raise regulation requirements have been increased.to manage frequency.
The following constraint set has been invoked.
F-MAIN_RREG_0450 at 1200 hrs.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 114528 is cancelled at 1445 hrs 12/02/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 13/02/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1700 hrs 13/02/2024 to 1830 hrs 13/02/2024.
The forecast capacity reserve requirement is 1224 MW.
The minimum capacity reserve available is 1098 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations