Inter-regional transfer limit variation - Moorabool Sydenham No1 500 kV line - Vic region - 25/02/2024
At 1929 hrs 25/02/2024 in the Victoria region the Moorabool Sydenham No1 500 kV line returned to service on temporary towers.
The Moorabool Sydenham No2 500 kV line remains out of service
Constraint set changes.
Invoked:
V-MLSY_NOEMTT_R
Revoked:
V-X_MLSY_MLTS_TIE
This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1
V-SA
V-S-MNSP1
VIC1- NSW1
Refer Market Notices 114577, 114768, 114686 and 114770
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115087 has been updated at 1430 hrs 25/02/2024 to the following:
[1.] From 1800 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 1255 MW.
The minimum capacity reserve available is 1152 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115086 has been updated at 1430 hrs 25/02/2024 to the following:
[1.] From 1500 hrs 29/02/2024 to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 1402 MW.
The minimum capacity reserve available is 725 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115039 has been updated at 1445 hrs 24/02/2024 to the following:
[1.] From 1730 hrs 29/02/2024 to 1900 hrs 29/02/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 915 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 115040 has been updated at 1445 hrs 24/02/2024 to the following:
[1.] From 1500 hrs 29/02/2024 to 2130 hrs 29/02/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 700 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115025 is cancelled at 1845 hrs 23/02/2024.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 29/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 1530 hrs to 2130 hrs 29/02/2024.
The forecast capacity reserve requirement is 1698 MW.
The minimum capacity reserve available is 968 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 29/02/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs to 1830 hrs 29/02/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 1004 MW.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 23/02/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 115016 has been updated at 1315 hrs to the following:
[1.] From 1730 hrs 23/02/2024 to 1900 hrs 23/02/2024.
The forecast capacity reserve requirement is 1256 MW.
The minimum capacity reserve available is 1097 MW.
Manager NEM Real Time Operations