114500MARKET INTERVENTION11/02/2024 02:31:43 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 04/02/2024

Refer Market Notice 114245

The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs 11/02/2024

Manager NEM Real Time Operations
114480MARKET INTERVENTION10/02/2024 04:37:54 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0100 hrs 12/02/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
114475MARKET INTERVENTION10/02/2024 04:36:24 PM

Update - Direction - SA Region - 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 04/02/2024

Refer Market Notice 114458

The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114458MARKET INTERVENTION09/02/2024 04:04:43 PM

Update - Direction - SA Region - 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 04/02/2024

Refer Market Notice 114245

The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114446MARKET INTERVENTION08/02/2024 05:14:11 PM

Update - Direction - SA Region - 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 04/02/2024

Refer Market Notice 114245

The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114436INTER-REGIONAL TRANSFER08/02/2024 10:24:54 AM

Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Dapto - Marulan 8 Line - NSW region - 08/02/2024

At 1015 hrs 08/02/2024 there was a short notice outage of Dapto - Marulan 8 Line


The following constraint set(s) invoked at 1015 hrs 08/02/2024
N-DTMN_8_15M

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114429INTER-REGIONAL TRANSFER07/02/2024 07:06:39 PM

Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024

At 1850 hrs 07/02/2024 there was an unplanned outage of the South Pine SVC.

The following constraint set(s) invoked at 1855 hrs 07/02/2024
Q-SP_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
114420MARKET INTERVENTION07/02/2024 04:01:24 PM

Update - Direction - SA Region - 04/02/2024

AEMO ELECTRICITY MARKET NOTICE

Update - Direction - SA Region - 04/02/2024

Refer Market Notice 114245

The AEMO intervention event that commenced from interval ending 1635hrs on 04/02/2024 is continuing.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

Manager NEM Real Time Operations
114407INTER-REGIONAL TRANSFER06/02/2024 09:12:48 PM

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024

At 2102 hrs 06/02/2024 there was an unplanned outage of the Greenbank 275kV SVC

The following constraint set(s) invoked at 2110 hrs 06/02/2024
Q-GB_VC

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations