Market Notices

113636RESERVE NOTICE22/01/2024 07:39:41 PM

PDPASA - Cancellation of the Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR 1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113635 is cancelled at 1930 hrs 22/01/2024

Manager NEM Real Time Operations
113635RESERVE NOTICE22/01/2024 06:42:10 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 22/01/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1830 hrs.
The Actual LOR1 condition is forecast in Predispatch
The capacity reserve requirement is 986 MW
The minimum capacity reserve available is 969 MW

Manager NEM Real Time Operations
113634RESERVE NOTICE22/01/2024 07:38:01 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region [beginning] on 22/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113616 is cancelled at 1930 hrs 22/01/2024.

Manager NEM Real Time Operations
113616RESERVE NOTICE22/01/2024 05:20:20 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113601 has been updated at 1700 hrs to the following:

1.] From 1800 hrs 22/01/2024 to 1830 hrs 22/01/2024.
The forecast capacity reserve requirement is 1032 MW.
The minimum capacity reserve available is 995 MW.

[2.] From 1900 hrs 22/01/2024 to 1930 hrs 22/01/2024.
The forecast capacity reserve requirement is 990 MW.
The minimum capacity reserve available is 801 MW.


Manager NEM Real Time Operations
113609RESERVE NOTICE22/01/2024 04:01:23 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113556 has been updated at 1400 hrs 22/01/2024 to the following:

From 1730 hrs to 2000 hrs 26/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 730 MW.

AEMO Operations
113607RESERVE NOTICE22/01/2024 04:00:09 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113555 has been updated at 1400 hrs 22/01/2024 to the following:

From 1430 hrs to 2130 hrs 25/01/2024.
The forecast capacity reserve requirement is 1460 MW.
The minimum capacity reserve available is 843 MW

AEMO Operations
113604RESERVE NOTICE22/01/2024 03:59:05 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1700 hrs to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 1241 MW.
The minimum capacity reserve available is 1029 MW.

AEMO Operations
113603RESERVE NOTICE22/01/2024 03:58:00 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1730 hrs to 2030 hrs 25/01/2024.
The forecast capacity reserve requirement is 1244 MW.
The minimum capacity reserve available is 1180 MW.

AEMO Operations
113601RESERVE NOTICE22/01/2024 11:02:39 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 22/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113582 has been updated at 1100 hrs to the following:

[1.] From 1830 hrs 22/01/2024 to 2000 hrs 22/01/2024.
The forecast capacity reserve requirement is 1100 MW.
The minimum capacity reserve available is 690 MW.


Manager NEM Real Time Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm