Filter by category
Filter by Date
Forecast Minimum System Load (MSL1) condition in the VIC region on 09/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 09/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 - 1745 MW
- MSL2 - 1245 MW
- MSL3 - 745 MW
The regional demand is forecast to be below the MSL1 threshold for the following period:
1. From 1100 hrs to 1400 hrs 09/11/2024. Minimum regional demand is forecast to be 1488 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb .
AEMO is seeking a market response.
AEMO Operations
Forecast Minimum System Load MSL1 condition in the VIC Region on 05/11/2024
Forecast Minimum System Load MSL1 condition in the VIC Region on 05/11/2024
Update to Market Notice 119743 - AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC on 05/11/2024.
Minimum regional demand is forecast to be 1258 MW at 1300 hrs, and the advisory threshold is:
MSL1 - 1320 MW
MSL2 - 820 MW
MSL3 - 320 MW
The regional demand is forecast to be below the MSL1 threshold for the following period[s]:
From 1200 hrs 05/11/2024 to 1330 hrs 05/11/2024.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 0700 hrs 05/11/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Forecast Minimum System Load MSL2 condition in the VIC region on 10/11/2024
AEMO has detected that there is an elevated risk of insufficient demand to maintain a secure operating state in the VIC region on 10/11/2024.
Minimum System Load (MSL) conditions are forecast when regional demand is less than the relevant MSL threshold. The advisory MSL thresholds are:
- MSL1 = 1760 MW
- MSL2 = 1260 MW
- MSL3 = 760 MW
The regional demand is forecast to be below the MSL2 threshold for the following period:
From 1230 hrs 10/11/2024 to 1330 hrs 10/11/2024. Minimum regional demand is forecast to be 1236 MW at 1300 hrs.
Forecast regional demand (DEMAND50) is published in Short Term and Pre-Dispatch PASA region solution reports available on Market Data NEMWEB: https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/market-data-nemweb.
AEMO is seeking a market response.
AEMO Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119835
The TORRB4 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 04/11/2024.
The direction update is issued at 0755 hrs 04/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119836
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1630 hrs 04/11/2024.
The direction update is issued at 0755 hrs 04/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119831
The TORRB3 TORRENS ISLAN direction is now expected to stay in place until 1700 hrs 04/11/2024.
The direction update is issued at 2115 hrs 03/11/2024.
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN
Refer AEMO Electricity Participant Notice 119832
The TORRB4 TORRENS ISLAN direction is now expected to start at 0900 hrs 04/11/2024.
The direction update is issued at 2115hrs 03/11/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 119823
Direction is cancelled from: 2030 hrs 03/11/2024
Manager NEM Real Time Operations