Market Notices

120055RESERVE NOTICE07/11/2024 06:15:21 AM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 07/11/2024 to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1394 MW.

Manager NEM Real Time Operations
     
120053RESERVE NOTICE07/11/2024 02:51:46 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 120045 is cancelled at 0245 hrs 07/11/2024.

Manager NEM Real Time Operations
     
120052RESERVE NOTICE07/11/2024 02:49:06 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 120050 has been updated at 0245 hrs to the following:

[1.] From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1112 MW.
The minimum capacity reserve available is 743 MW.

Manager NEM Real Time Operations
     
120050RESERVE NOTICE07/11/2024 01:21:00 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 1119967 has been updated at 0115 hrs to the following:

[1.] From 1730 hrs 07/11/2024 to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 1104 MW.
The minimum capacity reserve available is 722 MW.

[2.] From 1830 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1116 MW.
The minimum capacity reserve available is 801 MW.

Manager NEM Real Time Operations
     
120045RESERVE NOTICE06/11/2024 09:11:26 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1730 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1293 MW.

Manager NEM Real Time Operations
     
120031MARKET INTERVENTION06/11/2024 05:57:50 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 119875

Direction is cancelled from: 1800 hrs 06/11/2024

Manager NEM Real Time Operations
     
120019MARKET INTERVENTION06/11/2024 05:07:43 PM

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - BARKER INLET PS

Refer to Market Notice 119875


In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - BARKER INLET PS at 1655 hrs 06/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 1700 hrs 06/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1800 hrs 06/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     
120016GENERAL NOTICE06/11/2024 04:57:21 PM

Cancellation of Project Energy Connect (PEC-1) testing on 6th November 2024

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 119963

The Project Energy Connect (PEC-1) testing on 6th November has now been cancelled.

Terry Liu
AEMO Operations
     
120014MARKET INTERVENTION06/11/2024 04:04:29 PM

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Direction - SA region to AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN

Refer to Market Notice 120012

In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).

Direction issued to: AGL SA Generation Pty Limited - TORRB4 TORRENS ISLAN at 1600 hrs 06/11/2024
Type of resource: generating unit
Required actions: Synchronise and follow dispatch targets at 0800 hrs 07/11/2024
Services provided: Voltage Control
Circumstances necessitating the Direction:Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 0400 hrs 08/11/2024 / further notice.

AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.

Manager NEM Real Time Operations
     