Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120047 is cancelled at 0245 hrs 07/11/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 07/11/2024
The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 1119967 has been updated at 0115 hrs to the following:
[1.] From 1730 hrs 07/11/2024 to 1800 hrs 07/11/2024.
The forecast capacity reserve requirement is 1104 MW.
The minimum capacity reserve available is 722 MW.
[2.] From 1830 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 1116 MW.
The minimum capacity reserve available is 801 MW.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 120044 has been updated at 0100 hrs to the following:
[1.] From 1800 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 702 MW.
The minimum capacity reserve available is 684 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: VIC1
Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV
Cancellation time: 06/11/2024 22:54
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 119969
Auto-generated on behalf of Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 07/11/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 07/11/2024 to 1830 hrs 07/11/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1293 MW.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 07/11/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following Period:
[1.] From 1730 hrs 07/11/2024 to 1900 hrs 07/11/2024.
The forecast capacity reserve requirement is 747 MW.
The minimum capacity reserve available is 589 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Armidale - Dumaresq 8C 330kV line and Armidale - Sapphire WF 8E 330kV line in NSW1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: NSW1
Lines: Armidale - Dumaresq 8C 330kV and Armidale - Sapphire WF 8E 330kV
Cancellation time: 06/11/2024 16:59
Constraint set(s) revoked:
N-ARDM_ARSR_1PH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
Refer AEMO Electricity Market Notice 119997
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation of Project Energy Connect (PEC-1) testing on 6th November 2024
Refer to market notice 119963
The Project Energy Connect (PEC-1) testing on 6th November has now been cancelled.
Terry Liu
AEMO Operations
Cancellation of the reclassification of a Non-Credible contingency event: Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line in VIC due to Lightning.
Cancellation of the reclassification of a Non-Credible contingency event as a Credible contingency event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any Lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: VIC
Lines: Rowville - Yallourn No. 7 220 kV Line and the Rowville - Yallourn No. 8 220 kV Line
Cancellation time: 16:30 hrs 06/11/2024
Constraint set(s) revoked:
V-ROYP78_R_N-2
Refer AEMO Electricity Market Notice 119964
Manager NEM Real Time Operations