Direction - SA region 06/08/2024
Direction - SA region 06/08/2024
Refer to Market Notice 117568
In accordance with section 116 of the National Electricity Law, AEMO is issuing a direction to AGL SA Generation Pty Limited. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a1)(1).
Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN at 1700 hrs 06/08/2024
Type of resource: generating unit
Required actions: synchronise and follow dispatch targets at 1030 hrs 07/08/2024
Services provided: Voltage Control
Circumstances necessitating the Direction: Voltage
Circumstances necessitating the Direction additional detail: intervention is required to maintain the power system in a secure operating state
Expected duration: 1430 hrs 07/08/2024
AGL SA Generation Pty Limited does not incur any civil monetary liability for a relevant action taken in accordance with this direction unless the action is taken in bad faith.
Manager NEM Real Time Operations
Update - Foreseeable AEMO intervention in SA region
Update - Foreseeable AEMO intervention in SA region
Refer AEMO Electricity Market Notice 117566
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1030 hrs 07/08/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
AEMO estimates that, in the absence of sufficient market response by 1700 hrs 06/08/2024, AEMO may need to intervene by issuing a direction.
Manager NEM Real Time Operations
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
Foreseeable AEMO intervention under clause 4.8.5A (a) of the NER in SA region
AEMO has identified a foreseeable circumstance that may require an AEMO intervention event in the SA region from 1030 hrs 07/08/2024.
The foreseeable circumstance requiring the need for intervention is Voltage.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the SA region - 05/08/2024
Cancellation of Actual (LOR1) condition in the SA region - 05/08/2024
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No. 117564 is cancelled at 2145 hrs 05/08/2024.
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024
Update - Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024
The actual LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 117563 has been updated at 2120 hrs to the following:
The Actual LOR1 condition is forecast to exist until 2130 hrs.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 377 MW.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 05/08/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 2030 hrs.
The Actual LOR1 condition is forecast to exist until 2100 hrs.
The capacity reserve requirement is 450 MW
The minimum capacity reserve available is 428 MW
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 01/08/2024
Cancellation - AEMO Intervention Event - SA region 01/08/2024
Refer to Market Notice 117525
The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 02/08/2024.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB3 TORRENS ISLAN
Refer to Market Notice 117529
Direction is cancelled from: 1430 hrs 02/08/2024
Manager NEM Real Time Operations
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Cancellation: Direction issued to: Synergen Power Pty Limited - MINTARO MINTARO GAS
Refer to Market Notice 117526
Direction is cancelled from: 1230 hrs 02/08/2024
Manager NEM Real Time Operations