Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024
Inter-regional transfer limit variation - South Pine SVC - QLD region - 07/02/2024
At 1850 hrs 07/02/2024 there was an unplanned outage of the South Pine SVC.
The following constraint set(s) invoked at 1855 hrs 07/02/2024
Q-SP_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024
Inter-regional transfer limit variation - Greenbank 275kV SVC - QLD region - 06/02/2024
At 2102 hrs 06/02/2024 there was an unplanned outage of the Greenbank 275kV SVC
The following constraint set(s) invoked at 2110 hrs 06/02/2024
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024
Cancellation of Actual (LOR1) condition in the QLD region - 06/02/2024
The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.114399 is cancelled at 1945 hrs 06/02/2024.
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024
Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024
The actual LOR1 condition in the Qld region advised in AEMO Electricity Market Notice No. 114397 has been updated at 1915 hrs 06/02/2024 to the following:
The Actual LOR1 condition is forecast to exist until 2000 hrs.
The forecast capacity reserve requirement is 1045 MW.
The minimum capacity reserve available is 950 MW.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 06/02/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.
The Actual LOR1 condition is forecast to exist until 1930 hrs
The capacity reserve requirement is 1095 MW
The minimum capacity reserve available is 892 MW
Manager NEM Real Time Operations
[EventId:202402061745_review] Prices for interval 06-Feb-2024 17:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1740 hrs on 6 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2024 17:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402061740_review] Prices for interval 06-Feb-2024 17:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1735 hrs on 6 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2024 17:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402061735_review] Prices for interval 06-Feb-2024 17:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 6 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2024 17:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202402061730_review] Prices for interval 06-Feb-2024 17:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1725 hrs on 6 February 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 06-Feb-2024 17:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.