Update Inter-Regional Transfer limit variation - Basslink 21/05/2024
Update Inter-Regional Transfer limit variation - Basslink
Refer AEMO Electricity Market Notice 116734
There was an unplanned outage of the Basslink interconnector at 0235 hrs. The Basslink interconnector has been returned to service.
The following constraint set was revoked at 0810 hrs 21/05/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Basslink 21/05/2024
Inter-Regional Transfer limit variation - Basslink
There has been an unplanned outage of the Basslink interconnector at 0235 hrs
The following constraint set was invoked at 0240 hrs 21/05/2024
I-BL_ZERO
The constraint set contains the following interconnector on the left hand side.
T-V-MNSP1
Manager NEM Real Time Operations
[EventId:202405191545_review] Prices for interval 19-May-2024 15:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1540 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191540_review] Prices for interval 19-May-2024 15:40 are subject to review
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:40.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191535_review] Prices for interval 19-May-2024 15:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 1530 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191530_review] Prices for interval 19-May-2024 15:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 1525 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191525_review] Prices for interval 19-May-2024 15:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 1520 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405191520_review] Prices for interval 19-May-2024 15:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 1515 hrs on 19 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024
Inter-regional transfer limit variation - Tamworth - Armidale No. 86 330 kV Line - NSW region - 19/05/2024
A planned outage of Tamworth - Armidale No. 86 330 kV Line in the NSW region was scheduled from 0800 hrs 07/05/2024 to 1800 hrs 20/05/2024.
The outage has been rescheduled to be completed by 1200 hrs 19/05/2024.
Constraint set(s) invoked:
N-ARTW_86
N-DM_SVC
N-TW_SVC
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
T-V-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.