113699RESERVE NOTICE24/01/2024 03:01:49 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.113670 has been updated at 1400 hrs 24/01/2024 to the following:



[1.] From 1730 hrs 26/01/2024 to 1830 hrs 26/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1398 MW.

[2.] From 2000 hrs 26/01/2024 to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1429 MW.

AEMO Operations
113697RESERVE NOTICE24/01/2024 12:53:54 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1500 hrs 25/01/2024 to 1530 hrs 25/01/2024.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1349 MW.


Manager NEM Real Time Operations
113691GENERAL NOTICE24/01/2024 10:22:05 AM

NEM Local Temperature Alerts for QLD from 24 Jan 2024 to 28 Jan 2024

AEMO ELECTRICITY MARKET NOTICE

AEMO's weather service provider has issued forecast temperatures equal to or greater than the NEM Local Temperature Alert Levels for listed weather stations below.

QLD
Dalby Ap (37+ Deg C): 25th Jan, 26th Jan, 27th Jan

The NEM Local Temperature Alert Levels are:

Launceston Ti Tree Bend: 33 Deg C, Dalby Airport: 37 Deg C, for all other selected weather stations: 39 Deg C.

AEMO requests Market Participants to:

1. review the weather forecast in the local area where their generating units / MNSP converter stations are located and,

2. if required, update the available capacity in their dispatch offers or availability submissions consistent with the forecast temperatures.

Further information is available at:

https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/nem-forecasting-and-planning/forecasting-and-reliability/projected-assessment-of-system-adequacy/nem-local-temperature-alerts

AEMO Operations Planning
113674RESERVE NOTICE23/01/2024 03:48:27 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 30/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1730 hrs to 2030 hrs 30/01/2024.
The forecast capacity reserve requirement is 1007 MW.
The minimum capacity reserve available is 790 MW.

AEMO Operations
113673RESERVE NOTICE23/01/2024 03:47:27 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 27/01/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1530 hrs to 2130 hrs 27/01/2024.
The forecast capacity reserve requirement is 1188 MW.
The minimum capacity reserve available is 966 MW.

AEMO Operations
113672RESERVE NOTICE23/01/2024 03:46:27 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 113603 has been updated at 1400 hrs 23/01/2024 to the following:

From 1700 hrs to 2030 hrs 25/01/2024.
The forecast capacity reserve requirement is 1241 MW.
The minimum capacity reserve available is 737 MW.

AEMO Operations
113671RESERVE NOTICE23/01/2024 03:45:26 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 25/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113607 has been updated at 1400 hrs 23/01/2024 to the following:

From 2100 hrs to 2130 hrs 25/01/2024.
The forecast capacity reserve requirement is 1735 MW.
The minimum capacity reserve available is 1332 MW.

AEMO Operations
113670RESERVE NOTICE23/01/2024 03:44:17 PM

STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 26/01/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 113609 has been updated at 1400 hrs 23/01/2024 to the following:

From 1700 hrs to 2030 hrs 26/01/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1240 MW.

AEMO Operations
113667MARKET SYSTEMS23/01/2024 02:28:57 PM

CHG0082564:EMMS - WebPortal

Change Number: CHG0082564
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - WebPortal
Change Title: Identity Service Site Transfer
Change Start Date & Time: 30/01/2024 11:00:00 AEST
Change End Date & Time: 30/01/2024 19:00:00 AEST
Outage Start Date & Time: 30/01/2024 13:10:00 AEST
Outage End Date & Time: 30/01/2024 13:30:00 AEST
Environment: Production
Participant Impact and Requirements: Identity Service is used by multiple systems for user authorisation and authentication.
Identity Service is mostly used by the following systems:
*MSATS
*APIs (EMMS, GBB, MSATS)
*WEM
*Markets Portal
Identity Service might have an intermittemt outage of maximum 5 minutes during the outage period impacting user login.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm